What is this project?
Proposed 132 KV Transmission Line from 132/33 KV Grid substation at Barbil to 2.4MTPA Pellet Plant at Tanto is a lapsed power project in Sundara Unit-12, Barbil, Kendujhar, Odisha. The site covers 94.9 acres.
Who is building it?
The applicant is Narbheram Power and Steel Private Limited.
Has it been approved?
No. The application was lapsed on 18 Jul 2023, so it is no longer under consideration.
Where is it?
In Sundara Unit-12, Barbil, Kendujhar, Odisha.
How big is it?
It has a stated cost of ₹21 crore; a site of 94.9 acres and 13.6 acres (5.5 ha) of forest land.
When was it filed?
The application was filed on 8 Dec 2022.
Project details
| Status | Lapsed |
|---|---|
| Status since | 18 Jul 2023 |
| Application filed | 8 Dec 2022 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Narbheram Power and Steel Private Limited |
| Land area | 94.9 acres (38.4 ha) |
| Forest land | 13.6 acres (5.5 ha) |
| Project cost | ₹21 crore |
| Village / locality | Sundara Unit-12 |
| Taluk / tehsil | Barbil |
| District | Kendujhar |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04565 |
In context
10 applications in Kendujhar since January 2022 are in the same category (Power): 1 approved, 5 filed or under review, and 4 withdrawn, lapsed or rejected. At 94.9 acres, this one is larger than 50% of them.
21 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sundara Unit-12, Barbil, Kendujhar, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 132 KV Transmission Line from 132/33 KV Grid substation at Barbil to… — lapsed, 900 m away
- Kasia Iron Ore & Dolomite Mining and Beneficiation Plant Project — environmental approval granted, 900 m away
- Diversion of 3.999 Ha. Non-Forest Land Recorded As Forest As on 25.10.1980… — lapsed, 900 m away
- Proposed 2.4 MTPA (1 x 2.4 MTPA) Pellet Plant by M/s Narbheram Power and Steel… — cleared for impact study, 1.2 km away
- Preliminary Exploration for Iron Ore in Kasia West Block, Kendujhar District,… — forest land use approved, 1.6 km away
- Diversion of 7.576 Ha forest land involved in the ML area of Roida II Iron Ore… — lapsed, 1.7 km away
- Diversion of 7.576 Ha (4.435 Ha. for mining and ancillary activities and… — lapsed, 1.8 km away
- Transfer of Environment Clearance for Production of 3.5 Mtpa Iron Ore From… — environmental approval granted, 1.8 km away
More from Narbheram Power and Steel Private Limited in Kendujhar
- Laying of Water Pipeline from Village Kandra to Tanto for 2.4 MTPA Pallet… — lapsed
- Laying of Water Pipeline from Village Kandra to Tanto for 2.4 MTPA Pallet… — lapsed
- Proposed 2.4 MTPA (1 x 2.4 MTPA) Pellet Plant by M/s Narbheram Power and Steel… — cleared for impact study
- Diversion of 7.576 Ha (4.435 Ha. for mining and ancillary activities and… — lapsed
- Proposed 132 KV Transmission Line from 132/33 KV Grid substation at Barbil to… — lapsed
- Diversion of 7.576 Ha forest land involved in the ML area of Roida II Iron Ore… — lapsed
8 Narbheram Power and Steel projects in Kendujhar
All 9 Narbheram Power and Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.