Quick answers
What is this project?
Expansion of Existing Steel Manufacturing Unit under para 7(ii)(a) of EIA Notification, 2006 in light of OM dated 11.04.2022 & 30.05.2022 (20% increase in production capacity w.r.t EC accorded) for M/s Vardhman Special Steels Limited located at Plot no. C-58, Industrial Focal Point, Phase-III, Ludhiana, Punjab is a proposed industrial project in Ludhiana, Ludhiana (West), Punjab. The site covers 27.7 acres.
Who is building it?
The applicant is Vardhman Special Steels Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Ludhiana, Ludhiana (West), Punjab.
How big is it?
It has a stated cost of ₹304 crore and a site of 27.7 acres.
When was it filed?
The application was filed on 23 Jun 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 19 Nov 2026 |
| Application filed | 23 Jun 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Vardhman Special Steels Limited |
| Land area | 27.7 acres (11.2 ha) |
| Project cost | ₹304 crore |
| Village / locality | Ludhiana |
| Taluk / tehsil | Ludhiana (West) |
| District | Ludhiana |
| State | Punjab |
| Location from | Site boundary on record |
| Our reference | WID-PB-01008 |
In context
98 applications in Ludhiana since January 2022 are in the same category (Industry): 56 approved, 14 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 27.7 acres, this one is larger than 94% of them.
46 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ludhiana, Ludhiana (West), Punjab. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Regularization of existing Stand-Alone Rolling Mill via reheating furnace for… — lapsed, 650 m away
- Regularization of existing Stand-Alone Rolling Mill via reheating furnace for… — lapsed, 650 m away
- Expansion of Existing Electric Arc Furnace Capacity From 30 Tph to 35.5 Tph… — cleared for impact study, 850 m away
- Expansion of Existing Electric Arc Furnace Capacity From 32.3 Tph to 35.5 Tph… — lapsed, 850 m away
- Expansion of existing EAF capacity from 32.3 TPH to 35.5 TPH for increase in… — lapsed, 850 m away
- Expansion in the Existing Steel Manufacturing Unit by Increasing Capacity of… — lapsed, 850 m away
- Existing Steel Manufacturing Unit M/s Aarti Steel Limited (Rolling Mill… — cleared for impact study, 1 km away
- Existing Steel Manufacturing Unit M/s Aarti Steel Limited (Rolling Mill… — lapsed, 1 km away
About this information