Cleared for impact studyIndustry · Sikar, Rajasthan

Greenfield Steel Plant Project to produce Pellets 1.0 Million TPA; DRI 0.4 Million TPA, MS Billets 0.42 Million TPA and 0.4 Million TPA TMT Rebars with Iron ore beneficiation plant of capacity 2.65 Million TPA & Captive Power generation of 28 MW through WHRB and 15 MW through AFBC

Greenfield Steel Plant Project to produce Pellets 1.0 Million TPA; DRI 0.4 Million TPA, MS Billets 0.42 Million TPA and 0.4 Million TPA TMT Rebars with Iron ore beneficiation plant of capacity 2.65 Million TPA & Captive Power generation of 28 MW through WHRB and 15 MW through AFBC is a proposed industrial project in Garhtaknet, Sri Madhopur, Sikar, Rajasthan. The site covers 506 acres. Its stated project cost is ₹1,791.7 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 10 Aug 2024).

See it on the live map All projects in Sikar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Greenfield Steel Plant Project to produce Pellets 1.0 Million TPA; DRI 0.4 Million TPA, MS Billets 0.42 Million TPA and 0.4 Million TPA TMT Rebars with Iron ore beneficiation plant of capacity 2.65 Million TPA & Captive Power generation of 28 MW through WHRB and 15 MW through AFBC is a proposed industrial project in Garhtaknet, Sri Madhopur, Sikar, Rajasthan. The site covers 506 acres.

Who is building it?

The applicant is Geetanjali Steel Private Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 10 Aug 2024), as of 27 Nov 2026.

Where is it?

In Garhtaknet, Sri Madhopur, Sikar, Rajasthan.

How big is it?

It has a stated cost of ₹1,791.7 crore and a site of 506 acres.

When was it filed?

The application was filed on 26 Apr 2024.

One of 3 filings for this project. The project's main page, with every filing and where each stands: Greenfield Steel Plant Project to produce Pellets 1.0 Million TPA; DRI 0.4 Million TPA,…

Project details

Official titleGreenfield Steel Plant Project to produce Pellets 1.0 Million TPA; DRI 0.4 Million TPA, MS Billets 0.42 Million TPA and 0.4 Million TPA TMT Rebars with Iron ore beneficiation plant of capacity 2.65 Million TPA & Captive Power generation of 28 MW through WHRB and 15 MW through AFBC at Village Garh Taknet, Tehsil Sri Madhopur, District Neem ka Thana, Rajasthan
StatusCleared for impact study
Status since10 Aug 2024
Application filed26 Apr 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantGeetanjali Steel Private Limited
Land area506 acres (204.8 ha)
Project cost₹1,791.7 crore
Village / localityGarhtaknet
Taluk / tehsilSri Madhopur
DistrictSikar
StateRajasthan
Location fromSite boundary on record
Our referenceWID-RJ-14288

All filings for this project

This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Early planning filed 26 Apr 2024 (this page)Cleared for impact study506 acres₹1,791.7 crore
Early planning filed 6 Mar 2024Withdrawn506 acres₹1,770 crore
Early planning filed 31 Aug 2023Withdrawn506 acres₹1,772.1 crore

In context

5 applications in Sikar since January 2022 are in the same category (Industry): 3 approved, 0 filed or under review, and 2 withdrawn, lapsed or rejected.

1 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Garhtaknet, Sri Madhopur, Sikar, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 3 Geetanjali Steel projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.