What is 400 kV D/c Neemuch - Mandsaur Transmission line?
400 kV D/c Neemuch - Mandsaur Transmission line is a lapsed power project in Kanthariya, Begun, Chittaurgarh, Rajasthan. It seeks 48.1 acres of forest land.
Who is building it?
The applicant is Powergrid Neemuch Transmission System Limited.
Has it been approved?
No. The application was lapsed on 14 Sept 2023, so it is no longer under consideration.
Where is it?
In Kanthariya, Begun, Chittaurgarh, Rajasthan.
How big is it?
It has a stated cost of ₹3.1 crore and 48.1 acres (19.5 ha) of forest land.
When was it filed?
The application was filed on 2 Jun 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 14 Sept 2023 |
| Application filed | 2 Jun 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Powergrid Neemuch Transmission System Limited |
| Forest land | 48.1 acres (19.5 ha) |
| Project cost | ₹3.1 crore |
| Village / locality | Kanthariya |
| Taluk / tehsil | Begun |
| District | Chittaurgarh |
| State | Rajasthan |
| Location from | Site boundary on record |
| Our reference | WID-RJ-36409 |
In context
12 applications in Chittaurgarh since January 2022 are in the same category (Power): 6 approved, 1 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 19 months from filing to approval.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kanthariya, Begun, Chittaurgarh, Rajasthan. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Construction of 400 kV D/C Neemuch(PS)_Pachora(PS) Transmission line — lapsed, 3.9 km away
- 400 kV D/C Neemuch Pooling Station -Mandsaur Transmission Line — lapsed, 6.2 km away
- 400kV D/C Neemuch Mandsaur Transmission Line — forest land use approved, 6.9 km away
- Strengthening & Widening Work of Road Tolu Ka Luhariya to M.P. Border Via… — lapsed, 9 km away
- Tal-Kojya Road (Parlai) to Dungarpur, Timriya — lapsed, 13.4 km away
- Construction of 400 kV D/C Neemuch(PS) - Pachora(PS) Transmission line — more information requested, 14 km away
- Laying of Pipe Line Water Supply Project of 648 villages in Block Begun… — decision issued, 23.4 km away
- Laying of Pipe Line Water Supply Project of 648 villages in Block Begun… — more information requested, 23.4 km away
More from Powergrid Neemuch Transmission System Limited in Chittaurgarh
- 400kV D/C Neemuch Mandsaur Transmission Line — forest land use approved
- 400 KV D/C Neemuch PS- Chittorgarh (PG) Transmission Line in Rajasthan — forest land use approved
- 400 kV DC Neemuch- Chittorgarh Transmission Line in Rajasthan State — lapsed
4 Powergrid Neemuch Transmission projects in Chittaurgarh
All 5 Powergrid Neemuch Transmission projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.