One of 2 filings for this project. The project's main page, with every filing and where each stands: Bypass in (NH 310a) to Nhdl Specification With Paved Shoulder From Chungthang of Design…
Project details
| Official title | Construction of Bypass in (NH 310a) to Nhdl Specification With Paved Shoulder From Chungthang of Design Km 0+000 to Chungthang of Design Km 1+335 in the State of Sikkim Under Project Swastik of Bro |
|---|---|
| Status | Lapsed |
| Status since | 7 Nov 2022 |
| Application filed | 7 Nov 2022 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Bro/758 Brtf |
| Land area | 7.9 acres (3.2 ha) |
| Forest land | 2.6 acres (1.1 ha) |
| Project cost | ₹96.6 crore |
| Village / locality | Chungthang |
| Taluk / tehsil | Chungthang |
| District | North District |
| State | Sikkim |
| Location from | Site boundary on record |
| Our reference | WID-SK-00133 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 12 Jul 2023 | More information requested | ₹96.6 crore | |
| New project filed 7 Nov 2022 (this page) | Lapsed | 7.9 acres | ₹96.6 crore |
In context
15 applications in North District since January 2022 are in the same category (Roads & highways): 3 approved, 5 filed or under review, and 6 withdrawn, lapsed or rejected. At 7.9 acres, this one is smaller than 77% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Chungthang, North District, Sikkim. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Bypass in (NH 310a) to Nhdl Specification With Paved Shoulder From Chungthang… — more information requested, 250 m away
- Diversion of 0.1340 ha of forest land for const of Sewerage Treatment Plant at… — forest land use approved, 650 m away
- Granting Permission for laying OFC Cable through Overhead Methodology from… — lapsed, 2.6 km away
- Granting Permission for laying OFC Cable through Overhead Methodology from… — lapsed, 2.6 km away
- Construction/Improvement on Epc Mode of Existing Road to Nhdl Specification… — lapsed, 3.1 km away
- Teesta Hydroelectric Project Stage-III (1200 MW) — environmental approval granted, 4.9 km away
- Teesta Hydroelectric Project Stage-III (1200 MW) — withdrawn, 4.9 km away
- Diversion of forest land of 0.016 ha for construction of Plastic Waste… — more information requested, 6.1 km away
More from Bro/758 Brtf in North District
- Construction/Improvement on Epc Mode of Existing Road to Nhdl Specification… — lapsed
- Construction/ Improvement of NH 310ag to Nhdl Specification With Paved… — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.