6MW Mini Hydel Project at Kuntala Water Fall for Producing of Non Conventional Energy for Utilization With Water Pressure and Development Without Polluting the Natural Resources Falling is a proposed project in Kuntala Khurd, Neradigonda, Adilabad, Telangana. The site covers 0.8 acres.
Who is building it?
The applicant is Raji Power PIVATE Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Kuntala Khurd, Neradigonda, Adilabad, Telangana.
How big is it?
It has a stated cost of ₹60 crore and a site of 0.8 acres.
When was it filed?
The application was filed on 28 Oct 2024.
Project details
| Official title | Establishment of 6MW Mini Hydel Project at Kuntala Water Fall for Producing of Non Conventional Energy for Utilization With Water Pressure and Development Without Polluting the Natural Resources Falling in Kuntala Rf of Adilabad District. |
|---|---|
| Status | More information requested |
| Status since | 28 Oct 2024 |
| Application filed | 28 Oct 2024 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Other |
| Applicant | Raji Power PIVATE Limited |
| Land area | 3,100 m² |
| Project cost | ₹60 crore |
| Village / locality | Kuntala Khurd |
| Taluk / tehsil | Neradigonda |
| District | Adilabad |
| State | Telangana |
| Location from | Site boundary on record |
| Our reference | WID-TG-04495 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 20 May 2025 | Lapsed | 0.8 acres | ₹60 crore |
| New project filed 28 Oct 2024 (this page) | More information requested | 0.8 acres | ₹60 crore |
In context
8 applications in Adilabad since January 2022 are in the same category (Other): 0 approved, 4 filed or under review, and 4 withdrawn, lapsed or rejected.
Where it is
Kuntala Khurd, Neradigonda, Adilabad, Telangana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 6MW Mini Hydel Project at Kuntala Water Fall for Producing of Non Conventional… — lapsed, 0 m away
- Conversion of Existing Single Phase Supply to 3-Phase Supply by Laying of Abc… — lapsed, 6.7 km away
- Conversion of Existing Single Phase Supply to 3-Phase Supply by Laying of Abc… — more information requested, 6.7 km away
- Implementation of Advanced Traffic Management System (Atms) Work Through "land… — initial checks, 7.4 km away
- Diversion of 1.764 Ha of Forest Land in Echoda Division for Upgradation and… — under wildlife review, 7.9 km away
- Diversion of 0.40835 Ha of Forest Land for Construction of 4G Mobile Tower and… — forest land use approved, 9.5 km away
- Diversion of 0.042 Ha of Forest Land for Construction of 4G Mobile Tower and… — under wildlife review, 11.5 km away
- Diversion of 0.042 Ha of Forest Land for Construction of 4G Mobile Tower and… — forest land use approved, 11.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.