Quick answers
What is this project?
The Executive Engineer (Public Works Department / Water Resources Department - Nanganjiyar Basin Division) over an Extent of 25.31.7 ha of Government land in S.F.No. 225, 226 and 227, of Vadakadu Village of Oddanchatram Taluk, Dindigul District, Tamil Nadu State is an approved mining project in Reserved Forest, Oddanchatram, Dindigul, Tamil Nadu. The site covers 62.5 acres.
Who is building it?
The applicant is The Executive Engineer Pwd Palani.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 11 May 2023), as of 27 Nov 2026.
Where is it?
In Reserved Forest, Oddanchatram, Dindigul, Tamil Nadu.
How big is it?
It has a stated cost of ₹41 lakh and a site of 62.5 acres.
When was it filed?
The application was filed on 11 May 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 May 2023 |
| Application filed | 11 May 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | The Executive Engineer Pwd Palani |
| Land area | 62.5 acres (25.3 ha) |
| Project cost | ₹41 lakh |
| Village / locality | Reserved Forest |
| Taluk / tehsil | Oddanchatram |
| District | Dindigul |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-00626 |
In context
185 applications in Dindigul since January 2022 are in the same category (Mining): 121 approved, 36 filed or under review, and 27 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 62.5 acres, this one is larger than 98% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Reserved Forest, Oddanchatram, Dindigul, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Permission to remove desilting in Parappalar Dam IN DINDIGUL DISTRICT — forest land use approved, 150 m away
- Permission to remove desilting in Parappalar Dam IN DINDIGUL DISTRICT — lapsed, 150 m away
- Proposed Rough Stone Quarry of Thiru.P.Balakarthick — environmental approval granted, 5.4 km away
- Roughstone Quarry of Thiru P.Palanisamy — environmental approval granted, 5.4 km away
- Rough stone quarry of Thiru K.Rajaram — more information requested, 7.5 km away
- Laying of Overhead OFC cable in Periyur - Pachalur Section across Mulaiyar RF… — lapsed, 7.5 km away
- Laying of Overhead OFC cable in Periyur - Pachalur Section across Mulaiyar RF… — lapsed, 7.5 km away
- Laying of Underground OFC in Periyur - Pachalur Section across Mulaiyar RF -… — lapsed, 8.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.