What is Rough stone quarry of Thiru K.Rajaram?
Rough stone quarry of Thiru K.Rajaram is a proposed mining project in Reddiyapatti, Oddanchatram, Dindigul, Tamil Nadu. The site covers 4.4 acres.
Who is building it?
The applicant is Rajaram Kalipommu.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Reddiyapatti, Oddanchatram, Dindigul, Tamil Nadu.
How big is it?
It has a stated cost of ₹3.7 crore and a site of 4.4 acres.
When was it filed?
The application was filed on 3 Aug 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 6 Nov 2026 |
| Application filed | 3 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Rajaram Kalipommu |
| Land area | 4.4 acres (1.8 ha) |
| Project cost | ₹3.7 crore |
| Village / locality | Reddiyapatti |
| Taluk / tehsil | Oddanchatram |
| District | Dindigul |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-04917 |
In context
185 applications in Dindigul since January 2022 are in the same category (Mining): 121 approved, 36 filed or under review, and 27 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 4.4 acres, this one is smaller than 56% of them.
No other mining lease on record is within 500 m of this site; 2 have applied within 5 km.
Where it is
Reddiyapatti, Oddanchatram, Dindigul, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Rough Stone Quarry of Thiru.P.Balakarthick — environmental approval granted, 2.4 km away
- Roughstone Quarry of Thiru P.Palanisamy — environmental approval granted, 2.4 km away
- The Executive Engineer (Public Works Department / Water Resources Department -… — environmental approval granted, 7.5 km away
- Permission to remove desilting in Parappalar Dam IN DINDIGUL DISTRICT — forest land use approved, 7.6 km away
- Permission to remove desilting in Parappalar Dam IN DINDIGUL DISTRICT — lapsed, 7.6 km away
- Proposed Rough Stone Quarry of Thiru.C.Ranjith Kumar — environmental approval granted, 11.6 km away
- Rough Stone Quarry Project Belongs to M/s. Sri Aathithya Infra Project Pvt.… — environmental approval granted, 12.2 km away
- Ordinary Earth quarry of Tvl. Jawahar Constructions, Managing Partner: Thiru.… — environmental approval granted, 14.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.