What is Developing? Open the mapMap

Environmental approval grantedPower · Thoothukkudi, Tamil Nadu

Transfer of the Environmental Clearance accorded by SEIAA, Tamil Nadu by Lr. No. SEIAA/TN/EC/1(d)/013/F.No.282/2010 dated 10.11.2010 & amendment issued vide Lr. No. SEIAA/TN/EC/Amendment/F.No.282/2010 dated 20.12.2010 from M/s Ind-Bharat Thermal Power Limited to M/s Orissa Alloy Steel Private Limited, limited to the facilities already implemented within the EC validity i.e. 2 x 150 MW coal based Power plant

Transfer of the Environmental Clearance accorded by SEIAA, Tamil Nadu by Lr. No. SEIAA/TN/EC/1(d)/013/F.No.282/2010 dated 10.11.2010 & amendment issued vide Lr. No. SEIAA/TN/EC/Amendment/F.No.282/2010 dated 20.12.2010 from M/s Ind-Bharat Thermal Power Limited to M/s Orissa Alloy Steel Private Limited, limited to the facilities already implemented within the EC validity i.e. 2 x 150 MW coal based Power plant is an approved power project in Swaminatham, Ottapidaram, Thoothukkudi, Tamil Nadu. The site covers 225 acres. Its stated project cost is ₹1,173.6 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 16 Jun 2025).

See it on the live map All projects in Thoothukkudi

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Transfer of the Environmental Clearance accorded by SEIAA, Tamil Nadu by Lr. No. SEIAA/TN/EC/1(d)/013/F.No.282/2010 dated 10.11.2010 & amendment issued vide Lr. No. SEIAA/TN/EC/Amendment/F.No.282/2010 dated 20.12.2010 from M/s Ind-Bharat Thermal Power Limited to M/s Orissa Alloy Steel Private Limited, limited to the facilities already implemented within the EC validity i.e. 2 x 150 MW coal based Power plant is an approved power project in Swaminatham, Ottapidaram, Thoothukkudi, Tamil Nadu. The site covers 225 acres.

Who is building it?

The applicant is Orissa Alloy Steel PVT. LTD..

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 16 Jun 2025), as of 27 Nov 2026.

Where is it?

In Swaminatham, Ottapidaram, Thoothukkudi, Tamil Nadu.

How big is it?

It has a stated cost of ₹1,173.6 crore and a site of 225 acres.

When was it filed?

The application was filed on 3 Oct 2024.

Project details

StatusEnvironmental approval granted
Status since16 Jun 2025
Application filed3 Oct 2024
Approval soughtEnvironmental approval
Application typeOwnership transfer
SectorPower
ApplicantOrissa Alloy Steel PVT. LTD.
Land area225 acres (91.1 ha)
Project cost₹1,173.6 crore
Village / localitySwaminatham
Taluk / tehsilOttapidaram
DistrictThoothukkudi
StateTamil Nadu
Location fromSite boundary on record
Our referenceWID-TN-02546

In context

15 applications in Thoothukkudi since January 2022 are in the same category (Power): 9 approved, 3 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 225 acres, this one is smaller than 92% of them.

15 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Swaminatham, Ottapidaram, Thoothukkudi, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Orissa Alloy Steel PVT. LTD. in Thoothukkudi

All 12 Orissa Alloy Steel projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.