What is Tiuni Plasu HEP (72 MW)?
Tiuni Plasu HEP (72 MW) is an approved water and irrigation project in R F, Tyuni, Dehradun, Uttarakhand. The site covers 242.2 acres.
Who is building it?
The applicant is Ujvn Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 13 Nov 2026), as of 27 Nov 2026.
Where is it?
In R F, Tyuni, Dehradun, Uttarakhand.
How big is it?
It has a stated cost of ₹905.8 crore; a site of 242.2 acres and 117.5 acres (47.5 ha) of forest land.
When was it filed?
The application was filed on 21 Aug 2023.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 13 Nov 2026 |
| Application filed | 21 Aug 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Ujvn Limited |
| Land area | 242.2 acres (98 ha) |
| Forest land | 117.5 acres (47.5 ha) |
| Project cost | ₹905.8 crore |
| Village / locality | R F |
| Taluk / tehsil | Tyuni |
| District | Dehradun |
| State | Uttarakhand |
| Location from | Site boundary on record |
| Our reference | WID-UK-01363 |
In context
16 applications in Dehradun since January 2022 are in the same category (Water & irrigation): 5 approved, 6 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 2.8 years from filing to approval. At 242.2 acres, this one is larger than 83% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
R F, Tyuni, Dehradun, Uttarakhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Widening of NH 72B (707) Km. 133.150 to 173.600 (Portion Km 0/00 to 165.00)… — lapsed, 3.8 km away
- Dhamich Motor Road From Village Purtad Darmigad to Dhamich Kheda of Village… — initial checks, 5.8 km away
- Construciton of pedestrian brige over Tons River near Bhankwar Khudd in Block… — initial checks, 6.2 km away
- Arakot Tiuni Hydroelectric Project (81MW) — under environmental review, 6.6 km away
- Pyunal Water Supply Scheme — lapsed, 8.3 km away
- Dungri Penuwa Water Supply Scheme — more information requested, 13.4 km away
- Ofc Bharat Net Project — under forest review, 20.3 km away
- Ofc Bharat Net Project — initial checks, 23.9 km away
More from Ujvn Limited in Dehradun
- Arakot Tiuni Hydroelectric Project (81MW) — under environmental review
All 9 Ujvn projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.