One of 2 filings for this project. The project's main page, with every filing and where each stands: Environmental Clearance for the Expansion of Existing Production Capacity of Tmt Bar/Ms…
Project details
| Official title | Environmental Clearance for the Expansion of Existing Production Capacity of Tmt Bar/Ms Bar From 54000 Mta to 110000 Mta Through Continuous Casting Machine (Ccm) and Installation of Two Induction Furnace of Capacity 15 Mt Each for Manufacturing of M.S Billets/M.S. Ingot Having Installed Capacity 118800 Mta at Village Salarpur, Tehsil - Jansath, District - Muzaffarnagar – 251314 by M/S Swarup Rolling Mills Limited. |
|---|---|
| Status | Cleared for impact study |
| Status since | 10 Nov 2022 |
| Application filed | 10 Nov 2022 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Swarup Rolling Mills Limited |
| Land area | 7.5 acres (3 ha) |
| Project cost | ₹33.3 crore |
| Village / locality | Salarpur |
| Taluk / tehsil | Jansath |
| District | Muzaffarnagar |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-00106 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 6 Feb 2024 | Environmental approval granted | 7.5 acres | ₹33.3 crore |
| Early planning filed 10 Nov 2022 (this page) | Cleared for impact study | 7.5 acres | ₹33.3 crore |
In context
47 applications in Muzaffarnagar since January 2022 are in the same category (Industry): 30 approved, 5 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 7.5 acres, this one is smaller than 57% of them.
Where it is
Salarpur, Jansath, Muzaffarnagar, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environmental Clearance for the Expansion of Existing Production Capacity of… — environmental approval granted, 0 m away
- Amended BharatNet Project (Morna-Shakumbri-Muzzafarnagar) — lapsed, 5.7 km away
- Ordinary Soil Mining Project — lapsed, 5.7 km away
- Forest Land Proposed to be diverted for 132KV Transmission line from Jansath… — under wildlife review, 6.3 km away
- Proposed Protected Forest Land to be Re- diverted for Laying of steel Gas… — lapsed, 7.1 km away
- Proposed Protected Forest Land to be Re- diverted for Laying of steel Gas… — lapsed, 7.1 km away
- Rediversion of 0.9960 Ha PF LAND in favour of M/S Indarprastha Gas Ltd. New… — forest land use approved, 7.5 km away