What is Developing? Open the mapMap

Cleared for impact studyMining · Mahoba, Uttar Pradesh

Building stone (Granite-Khanda-Boulder-Ballast(Gitty))" Mine at Gata/Arazi No-339, Khand no.-37, Village– Daharra, Tehsil & District–Mahoba, Uttar Pradesh By M/s V.R. Infrabuild India Pvt. Ltd. (Shri Jitendra Singh Bhadoriya)

Building stone (Granite-Khanda-Boulder-Ballast(Gitty))" Mine at Gata/Arazi No-339, Khand no.-37, Village– Daharra, Tehsil & District–Mahoba, Uttar Pradesh By M/s V.R. Infrabuild India Pvt. Ltd. (Shri Jitendra Singh Bhadoriya) is a proposed mining project in Daharra, Mahoba, Uttar Pradesh. The site covers 4 acres. Its stated project cost is ₹1.5 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 7 May 2023).

See it on the live map All projects in Mahoba

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Building stone (Granite-Khanda-Boulder-Ballast(Gitty))" Mine at Gata/Arazi No-339, Khand no.-37, Village– Daharra, Tehsil & District–Mahoba, Uttar Pradesh By M/s V.R. Infrabuild India Pvt. Ltd. (Shri Jitendra Singh Bhadoriya) is a proposed mining project in Daharra, Mahoba, Uttar Pradesh. The site covers 4 acres.

Who is building it?

The applicant is V R Infrabuild India Private Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 7 May 2023), as of 27 Nov 2026.

Where is it?

In Daharra, Mahoba, Uttar Pradesh.

How big is it?

It has a stated cost of ₹1.5 crore and a site of 4 acres.

When was it filed?

The application was filed on 7 May 2023.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Building stone (Granite-Khanda-Boulder-Ballast(Gitty))" Mine at Gata/Arazi No-339, Khand…

Project details

StatusCleared for impact study
Status since7 May 2023
Application filed7 May 2023
Approval soughtEnvironmental approval
Application typeEarly planning
SectorMining
ApplicantV R Infrabuild India Private Limited
Land area4 acres (1.6 ha)
Project cost₹1.5 crore
Village / localityDaharra
Taluk / tehsilMahoba
DistrictMahoba
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-00779

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 27 Dec 2023Environmental approval granted4 acres₹1.5 crore
Early planning filed 7 May 2023 (this page)Cleared for impact study4 acres₹1.5 crore

In context

310 applications in Mahoba since January 2022 are in the same category (Mining): 251 approved, 27 filed or under review, and 32 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 4 acres, this one is larger than 64% of them.

12 other mining leases have applied within 500 m of this site; together with this one they cover 41.4 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 37 mining leases have applied within 5 km.

Where it is

Daharra, Mahoba, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from V R Infrabuild India Private Limited in Mahoba

All 4 V R Infrabuild projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.