One of 3 filings for this project. The project's main page, with every filing and where each stands: Riverbed Ordinary sand mining" having lease area- 6.8250 ha along river Garra at Gata…
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 16 May 2023 |
| Application filed | 16 May 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Ganga Ram |
| Land area | 8.2 acres (3.3 ha) |
| Project cost | ₹95 lakh |
| Village / locality | Pariyal Pansala |
| Taluk / tehsil | Shahabad |
| District | Hardoi |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-01370 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 13 Sept 2025 | Cleared for impact study | 16.9 acres | ₹95 lakh |
| New project filed 1 Apr 2024 | Environmental approval granted | 8.2 acres | ₹95 lakh |
| Early planning filed 16 May 2023 (this page) | Cleared for impact study | 8.2 acres | ₹95 lakh |
In context
22 applications in Hardoi since January 2022 are in the same category (Mining): 11 approved, 11 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 8.2 acres, this one is larger than 77% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Pariyal Pansala, Shahabad, Hardoi, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Riverbed Ordinary sand mining" having lease area- 6.8250 ha along river Garra… — environmental approval granted, 0 m away
- Riverbed Ordinary sand mining" having lease area- 6.8250 ha along river Garra… — cleared for impact study, 50 m away
- Proposed Protected Forest Land to be diverted for Laying of Gas Pipe Line… — more information requested, 6.5 km away
- Expansion of Existing Sugar Unit From 7500 Tcd to 15,000 Tcd — environmental approval granted, 13.7 km away
- Expansion of Existing Sugar Unit From 7500 Tcd to 15,000 Tcd — cleared for impact study, 13.7 km away
- Protected Forest Land Proposed to Be Diverted for Entry and Exit Approach to… — more information requested, 17.5 km away
- Proposed Integrated Manufacturing & Logistic Cluster (IMLC) Hardoi at Villages… — initial checks, 25.1 km away
- Proposed Integrated Manufacturing & Logistic Cluster (IMLC) Hardoi at Villages… — cleared for impact study, 25.1 km away
About this information