What is Developing? Open the mapMap

Cleared for impact studyIndustry · Bijnor, Uttar Pradesh

Proposed expansion of Sugar unit from 14000 TCD to 15000 TCD without change in Co gen power plant – 60 MW within existing premises

Proposed expansion of Sugar unit from 14000 TCD to 15000 TCD without change in Co gen power plant – 60 MW within existing premises is a proposed industrial project in Alhepur Veeran, Dhampur, Bijnor, Uttar Pradesh. The site covers 33.6 acres. Its stated project cost is ₹842.2 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 7 Mar 2025).

See it on the live map All projects in Bijnor

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Proposed expansion of Sugar unit from 14000 TCD to 15000 TCD without change in Co gen power plant – 60 MW within existing premises is a proposed industrial project in Alhepur Veeran, Dhampur, Bijnor, Uttar Pradesh. The site covers 33.6 acres.

Who is building it?

The applicant is Dhampur Sugar Mills Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 7 Mar 2025), as of 27 Nov 2026.

Where is it?

In Alhepur Veeran, Dhampur, Bijnor, Uttar Pradesh.

How big is it?

It has a stated cost of ₹842.2 crore and a site of 33.6 acres.

When was it filed?

The application was filed on 14 Dec 2024.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed expansion of Sugar unit from 14000 TCD to 15000 TCD without change in Co gen…

Project details

Official titleProposed expansion of Sugar unit from 14000 TCD to 15000 TCD without change in Co gen power plant – 60 MW within existing premises, at village – Alhepur, Block: Dhampur (Alehpur), Tehsil -Dhampur, District: Bijnor, Uttar Pradesh by M/s Dhampur Sugar Mills Ltd, (Unit: Dhampur).
StatusCleared for impact study
Status since7 Mar 2025
Application filed14 Dec 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantDhampur Sugar Mills Limited
Land area33.6 acres (13.6 ha)
Project cost₹842.2 crore
Village / localityAlhepur Veeran
Taluk / tehsilDhampur
DistrictBijnor
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-01776

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 24 Apr 2026Environmental approval granted33.6 acres₹842.2 crore
Early planning filed 14 Dec 2024 (this page)Cleared for impact study33.6 acres₹842.2 crore

In context

8 applications in Bijnor since January 2022 are in the same category (Industry): 5 approved, 3 filed or under review, and 0 withdrawn, lapsed or rejected.

3 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Alhepur Veeran, Dhampur, Bijnor, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 3 Dhampur Sugar Mills projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.