Cleared for impact studyIndustry · Balrampur, Uttar Pradesh

Expansion of existing Sugar unit from 7000 TCD to 10000 TCD and expansion in co gen power capacity from 3.0 MW to 17.0 MW within existing industry premises

Expansion of existing Sugar unit from 7000 TCD to 10000 TCD and expansion in co gen power capacity from 3.0 MW to 17.0 MW within existing industry premises is a proposed industrial project in Sitlapur, Tulsipur, Balrampur, Uttar Pradesh. The site covers 89.8 acres. Its stated project cost is ₹317.1 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 18 Mar 2024).

See it on the live map All projects in Balrampur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of existing Sugar unit from 7000 TCD to 10000 TCD and expansion in co gen power capacity from 3.0 MW to 17.0 MW within existing industry premises is a proposed industrial project in Sitlapur, Tulsipur, Balrampur, Uttar Pradesh. The site covers 89.8 acres.

Who is building it?

The applicant is Balrampur Chini Mills LTD.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 18 Mar 2024), as of 27 Nov 2026.

Where is it?

In Sitlapur, Tulsipur, Balrampur, Uttar Pradesh.

How big is it?

It has a stated cost of ₹317.1 crore and a site of 89.8 acres.

When was it filed?

The application was filed on 16 Mar 2024.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of existing Sugar unit from 7000 TCD to 10000 TCD and expansion in co gen…

Project details

Official titleExpansion of existing Sugar unit from 7000 TCD to 10000 TCD and expansion in co gen power capacity from 3.0 MW to 17.0 MW within existing industry premises at village: Shitlapur Tulsipur, District: Balrampur, Uttar Pradesh by M/s Balrampur Chini Mills Ltd, (Unit: Tulsipur, Division: Sugar)
StatusCleared for impact study
Status since18 Mar 2024
Application filed16 Mar 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantBalrampur Chini Mills LTD
Land area89.8 acres (36.3 ha)
Project cost₹317.1 crore
Village / localitySitlapur
Taluk / tehsilTulsipur
DistrictBalrampur
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-02539

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 29 Apr 2025Environmental approval granted89.8 acres₹317.1 crore
Early planning filed 16 Mar 2024 (this page)Cleared for impact study89.8 acres₹317.1 crore

In context

4 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Sitlapur, Tulsipur, Balrampur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Balrampur Chini Mills LTD in Balrampur

3 Balrampur Chini Mills projects in Balrampur
All 16 Balrampur Chini Mills projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.