What is Developing? Open the mapMap

Cleared for impact studyIndustry · Gorakhpur, Uttar Pradesh

PROPOSED GRAIN BASED ETHANOL DISTILLERY CAPACITY – 750 KLD AND MALT BASED DISTILLERY – 20 KLD by M/s SHREYAS DISTILLERIES AND ENERGY PVT LTD

PROPOSED GRAIN BASED ETHANOL DISTILLERY CAPACITY – 750 KLD AND MALT BASED DISTILLERY – 20 KLD by M/s SHREYAS DISTILLERIES AND ENERGY PVT LTD is a proposed industrial project in Bath Buzurg, Gola, Gorakhpur, Uttar Pradesh. The site covers 60.5 acres. Its stated project cost is ₹467.8 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 17 Jun 2026).

See it on the live map All projects in Gorakhpur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

One of 2 filings for this project. The project's main page, with every filing and where each stands: PROPOSED GRAIN BASED ETHANOL DISTILLERY CAPACITY – 750 KLD AND MALT BASED DISTILLERY –…

Project details

Official titleESTABLISHMENT OF PROPOSED GRAIN BASED ETHANOL DISTILLERY CAPACITY – 750 KLD AND MALT BASED DISTILLERY – 20 KLD ALONG WITH CO GEN POWER PLANT - 15 MW AT PLOT NO A – 3, SECTOR – S5, DHURIYAPAR INDUSTRIAL AREA, DISTT – GORAKHPUR (UP) BY M/s SHREYAS DISTILLERIES AND ENERGY PVT LTD
StatusCleared for impact study
Status since17 Jun 2026
Application filed20 Sept 2025
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantShreyas Distilleries & Energy Private Limited
Land area60.5 acres (24.5 ha)
Project cost₹467.8 crore
Village / localityBath Buzurg
Taluk / tehsilGola
DistrictGorakhpur
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-03103

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 18 Jun 2026Environmental approval granted60.5 acres₹467.8 crore
Early planning filed 20 Sept 2025 (this page)Cleared for impact study60.5 acres₹467.8 crore

In context

14 applications in Gorakhpur since January 2022 are in the same category (Industry): 13 approved, 1 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 60.5 acres, this one is smaller than 57% of them.

3 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Bath Buzurg, Gola, Gorakhpur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.