Expansion of Sponge Iron Plant(1,20,000 to 15,84,000 TPA),Captive Power Plant(10 MW to 145 MW–WHRB, AFBC & CFBC Boiler),Ferro Alloy(1x9 MVA to 8x9 MVA) is an approved industrial project in Babuijor, Santuri, Puruliya, West Bengal. The site covers 320.6 acres.
Who is building it?
The applicant is Sps Steels Rolling Mills Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 26 Feb 2024), as of 27 Nov 2026.
Where is it?
In Babuijor, Santuri, Puruliya, West Bengal.
How big is it?
It has a stated cost of ₹3,565 crore and a site of 320.6 acres.
When was it filed?
The application was filed on 22 Nov 2023.
Project details
| Official title | Expansion of Sponge Iron Plant(1,20,000 to 15,84,000 TPA),Captive Power Plant(10 MW to 145 MW–WHRB, AFBC & CFBC Boiler),Ferro Alloy(1x9 MVA to 8x9 MVA), along with New Installation of Steel Melting Shop(10,05,000 TPA),Rolling Mill(9,97,500 TPA),Pellet Plant(2x2.4 MTPA),Sinter Plant(1,00,000 TPA),Jigging plant(1,65,000 TPA),Briquetting plant(3,00,000 TPA),Oxygen Plant(170 TPD)&Railway Siding at Village Poradiha,Chandurdi&Shunurhi,PO–Pachhandapur,PS–Santuri,Tehsil Raghunathpur,District Purulia,WB |
|---|---|
| Status | Environmental approval granted |
| Status since | 26 Feb 2024 |
| Application filed | 22 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Sps Steels Rolling Mills Limited |
| Land area | 320.6 acres (129.8 ha) |
| Project cost | ₹3,565 crore |
| Village / locality | Babuijor |
| Taluk / tehsil | Santuri |
| District | Puruliya |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00104 |
In context
33 applications in Puruliya since January 2022 are in the same category (Industry): 22 approved, 5 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 320.6 acres, this one is larger than 64% of them.
Where it is
Babuijor, Santuri, Puruliya, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Sponge Iron Plant (1,76,000 TPA to 4,20,000 TPA), Ferro Alloy… — environmental approval granted, 5.7 km away
- Expansion of M/s Rabindra Enterprises Pvt Ltd for enhancement of sponge iron… — cleared for impact study, 9 km away
- Expansion of M/s Rabindra Enterprises Pvt Ltd for enhancement of sponge iron… — lapsed, 9 km away
- Expansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — cleared for impact study, 9 km away
- Expansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — cleared for impact study, 9 km away
- Xpansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — withdrawn, 9 km away
- Cluster no. 5 total production capacity of 0.42 in a ML area of 2291.0 Ha of… — lapsed, 9.6 km away
- Ambari Blackstone Mine — initial checks, 9.8 km away
All 4 Sps Steels Rolling Mills projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.