Quick answers
What is this project?
Expansion of Sponge Iron Plant (1,76,000 TPA to 4,20,000 TPA), Ferro Alloy Plant (30,000 TPA to 70,000 TPA) & Captive Power Plant (20 MW to 32 MW) is an approved industrial project in Bonra, Neturia, Puruliya, West Bengal. The site covers 44.8 acres.
Who is building it?
The applicant is Madhur Agarwalla.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 20 Nov 2023), as of 27 Nov 2026.
Where is it?
In Bonra, Neturia, Puruliya, West Bengal.
How big is it?
It has a stated cost of ₹352 crore and a site of 44.8 acres.
When was it filed?
The application was filed on 13 Sept 2023.
Project details
| Official title | Expansion of Sponge Iron Plant (1,76,000 TPA to 4,20,000 TPA), Ferro Alloy Plant (30,000 TPA to 70,000 TPA) & Captive Power Plant (20 MW to 32 MW) along with existing Iron Ore Sinter Plant (80,000 TPA) & Iron Ore Washery Plant (2,40,000 TPA) |
|---|---|
| Status | Environmental approval granted |
| Status since | 20 Nov 2023 |
| Application filed | 13 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Madhur Agarwalla |
| Land area | 44.8 acres (18.2 ha) |
| Project cost | ₹352 crore |
| Village / locality | Bonra |
| Taluk / tehsil | Neturia |
| District | Puruliya |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00347 |
In context
33 applications in Puruliya since January 2022 are in the same category (Industry): 22 approved, 5 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 44.8 acres, this one is smaller than 64% of them.
13 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bonra, Neturia, Puruliya, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of M/s Rabindra Enterprises Pvt Ltd for enhancement of sponge iron… — cleared for impact study, 3.4 km away
- Expansion of M/s Rabindra Enterprises Pvt Ltd for enhancement of sponge iron… — lapsed, 3.4 km away
- Expansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — cleared for impact study, 3.4 km away
- Expansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — cleared for impact study, 3.4 km away
- Xpansion of M/s Rabindra Enterprises Pvt. Ltd. for enhancement of sponge iron… — withdrawn, 3.4 km away
- Cluster no. 5 total production capacity of 0.42 in a ML area of 2291.0 Ha of… — lapsed, 4.5 km away
- Proposed expansion of existing steel plant — environmental approval granted, 4.5 km away
- Proposed Expansion of Existing Steel Plant. — environmental approval granted, 4.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.