| Status | Environmental approval granted |
|---|---|
| Status since | 25 Feb 2023 |
| Application filed | 25 Feb 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Satyam Iron & Steel Co Private Limited |
| Land area | 31 acres (12.6 ha) |
| Project cost | ₹230 crore |
| Village / locality | Mandalpur |
| Taluk / tehsil | Jamuria |
| District | Paschim Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00177 |
In context
169 applications in Paschim Bardhaman since January 2022 are in the same category (Industry): 81 approved, 49 filed or under review, and 39 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 31 acres, this one is larger than 50% of them.
68 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mandalpur, Jamuria, Paschim Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Sponge Iron Plant to Increase the Production Capacity From… — lapsed, 0 m away
- Expansion of Sponge Iron Plant to Increase the Production Capacity From… — cleared for impact study, 0 m away
- Expansion of Dual Re-Rolling MillPlant located at Plot No. 2966, 2968&… — lapsed, 350 m away
- Proposed ISP: Iron Ore Beneficiation Plant (2.8 MTPA), Pelletization Plant (2… — environmental approval granted, 600 m away
- Proposed ISP: Iron Ore Beneficiation Plant (2.8 MTPA), Pelletization Plant (2… — cleared for impact study, 600 m away
- Re-Rolling Mill Steel Plant located at R.S. & L.R. Plot No. 2849, 2861,… — not approved, 650 m away
- Re-Rolling Mill Steel Plant located at R.S. & L.R. Plot No. 2849, 2861,… — more information requested, 650 m away
- Environmental Clearance for Expansion of production capacity from 1,08,000 TPA… — environmental approval granted, 750 m away
More from Satyam Iron & Steel Co Private Limited in Paschim Bardhaman
- Expansion of Sponge Iron Plant to Increase the Production Capacity From… — lapsed
- Expansion Under 7(Ii)(A) in the Existing Steel Plant by Increasing the… — returned to applicant
- Expansion of Sponge Iron Plant to Increase the Production Capacity From… — cleared for impact study
All 8 Satyam Iron and Steel Co projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.