Quick answers
What is this project?
Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI Kilns, 8x20 T Induction Furnaces is an approved industrial project in Palitpur, Burdwan - I, Purba Bardhaman, West Bengal. The site covers 197.9 acres.
Who is building it?
The applicant is HMB Steel private limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 19 Jun 2026), as of 27 Nov 2026.
Where is it?
In Palitpur, Burdwan - I, Purba Bardhaman, West Bengal.
How big is it?
It has a stated cost of ₹810 crore and a site of 197.9 acres.
When was it filed?
The application was filed on 10 Feb 2026.
Project details
| Official title | Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI Kilns, 8x20 T Induction Furnaces along with matching LRF & CCM, 1x10 T AOD & 1x10 T VOD & 1X20 TPH capacity Slag Crusher Unit, 5x9 MVA capacity Submerged Arc Furnaces, 0.55 MTPA capacity Rolling Mill along with 1x30 TPH Re-heating Furnace (stand by) & 2x4000 Nm3/Hr capacity Producer Gas Plant (stand by), 60,000 TPA capacity Galvanising Unit and 30 MW capacity Captive Power Plant (24 MW WHRB + 6 MW AFBC). |
|---|---|
| Status | Environmental approval granted |
| Status since | 19 Jun 2026 |
| Application filed | 10 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | HMB Steel private limited |
| Land area | 197.9 acres (80.1 ha) |
| Project cost | ₹810 crore |
| Village / locality | Palitpur |
| Taluk / tehsil | Burdwan - I |
| District | Purba Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01668 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 10 Feb 2026 (this page) | Environmental approval granted | 197.9 acres | ₹810 crore |
| New project filed 18 Nov 2025 | Returned to applicant | 161.7 acres | ₹810 crore |
| Early planning filed 9 Apr 2025 | Cleared for impact study | 197.9 acres | ₹810 crore |
In context
21 applications in Purba Bardhaman since January 2022 are in the same category (Industry): 9 approved, 8 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 197.9 acres, this one is larger than 90% of them.
Where it is
Palitpur, Burdwan - I, Purba Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI… — cleared for impact study, 0 m away
- Durgapur Haldia Section of Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL)… — forest land use approved, 5.1 km away
- Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI… — returned to applicant, 10.5 km away
- IP-07(Panagarh) To Illambazar Natural Gas Pipeline (11A.03) — lapsed, 11.4 km away
- Ground Water Based Piped Water Supply Scheme for "jalikandar" Block:… — forest land use approved, 16.5 km away
- Transfer of Environmental Clearance for Proposed 100 KLPD Grain based… — environmental approval granted, 18.1 km away
- Proposed Expansion of Existing Grain Based Distillery Plant Capacity From 100… — initial checks, 18.1 km away
- Amarpur Piped Water Supply Scheme — forest land use approved, 18.4 km away
All 3 HMB Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.