Quick answers
What is this project?
Amendment in Environmental Clearance for Seeking review of applicability of Sulphur dioxide standards and exemption from installation of FGD as per MoEF&CC notification dated 11.07.2025 for 2×300 MW Coal Based Thermal Power Plant at Baneshwarchak, Haldia, District- Purba Medinipur, West Bengal is an approved power project in Baneswar Chak, Sutahata, Purba Medinipur, West Bengal. The site covers 375 acres.
Who is building it?
The applicant is Haldia Energy Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 11 May 2026), as of 27 Nov 2026.
Where is it?
In Baneswar Chak, Sutahata, Purba Medinipur, West Bengal.
How big is it?
It has a stated cost of ₹4,029.4 crore and a site of 375 acres.
When was it filed?
The application was filed on 5 Feb 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 11 May 2026 |
| Application filed | 5 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Power |
| Applicant | Haldia Energy Limited |
| Land area | 375 acres (151.8 ha) |
| Project cost | ₹4,029.4 crore |
| Village / locality | Baneswar Chak |
| Taluk / tehsil | Sutahata |
| District | Purba Medinipur |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01850 |
In context
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Baneswar Chak, Sutahata, Purba Medinipur, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Application for "No Increase in Pollution Load" Certificate for Product Mix… — initial checks, 1 km away
- Extension of validity of Environmental and CRZ clearance for "Development of… — returned to applicant, 1.6 km away
- 3.2 Km Stretch From Hall to Haldia Terminal for the Proposed Haldia-Panagarh… — coastal clearance granted, 4.6 km away
- Expansion of Fertilizer Plant located at Durgachak, Haldia, Purba Medinipur,… — more information requested, 5.2 km away
- Environmental Clearance transfer from M/s UPL Limited Unit 09 to M/s Superform… — environmental approval granted, 6.1 km away
- Change in product mix with No Increase in Pollution Load under Para 7 ii (b)… — initial checks, 6.1 km away
- Change in product mix with No Increase in Pollution Load under Para 7 ii (b)… — initial checks, 6.1 km away
- Proposed Expansion of UPL Limited - Haldia Manufacturing Unit — environmental approval granted, 6.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.