Project details
| Status | More information requested |
|---|---|
| Status since | 16 Apr 2026 |
| Application filed | 26 Aug 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Industry |
| Applicant | Shyam Sel & Power Limited |
| Land area | 35.2 acres (14.2 ha) |
| Forest land | 1.2 acres (0.5 ha) |
| Project cost | ₹164.3 crore |
| Village / locality | Dhasna |
| Taluk / tehsil | Jamuria |
| District | Paschim Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-02294 |
In context
169 applications in Paschim Bardhaman since January 2022 are in the same category (Industry): 81 approved, 49 filed or under review, and 39 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 35.2 acres, this one is larger than 56% of them.
69 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dhasna, Jamuria, Paschim Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- EXPANSION OF PRODUCTION CAPACITY OF COLD ROLLING MILL COMPLEX (CRMC) FROM… — environmental approval granted, 300 m away
- Transfer of Environmental Clearance for 5,88,800 Tpa Cold Rolling Mill Complex… — under environmental review, 300 m away
- ENVIRONMENT CLEARANCE FOR EXPANSION OF PRODUCTION CAPACITY OF COLD ROLLING… — environmental approval granted, 300 m away
- ENVIRONMENT CLEARANCE FOR EXPANSION OF PRODUCTION CAPACITY OF COLD ROLLING… — cleared for impact study, 300 m away
- Shyam Metalics Flat Product Pvt. Ltd.-Proposed project for Installation of… — lapsed, 300 m away
- Shyam Metalics Flat Product Pvt. Ltd.-Proposed project for Installation of… — cleared for impact study, 300 m away
- Industrial project by Shyam SEL and Power Limited — more information requested, 400 m away
- Diversion of 0.92 Ha of Forest Land by SPINTECH TUBES PRIVATE LIMITED — withdrawn, 600 m away
More from Shyam Sel & Power Limited in Paschim Bardhaman
- Transfer of Environmental Clearance for 5,88,800 Tpa Cold Rolling Mill Complex… — under environmental review
- Proposed Integrated Steel Plant — environmental approval granted
- "No Increase in Pollution Load" Certificate for Increasing of Production… — initial checks
- Industrial project by Shyam SEL and Power Limited — more information requested
- Proposed Expansion cum modification of Existing Steel Plant — returned to applicant
- Proposed Expansion cum modification of Existing Steel Plant — lapsed
9 Shyam Sel & Power projects in Paschim Bardhaman
All 16 Shyam Sel & Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.