Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 5 Aug 2024 |
| Application filed | 14 Jun 2023 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Power |
| Applicant | Chhattisgarh State Power Generation Company Limited |
| Land area | 670.3 acres (271.3 ha) |
| Project cost | ₹3,719 crore |
| Village / locality | Darri |
| Taluk / tehsil | Katghora |
| District | Korba |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00411 |
In context
27 applications in Korba since January 2022 are in the same category (Power): 10 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 670.3 acres, this one is smaller than 56% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Darri, Katghora, Korba, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking… — under environmental review, 350 m away
- Proposed Expansion by addition of 2 x 660 MW Supercritical Units of… — more information requested, 350 m away
- Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking… — more information requested, 400 m away
- Amendment of 1x500 MW coal based Thermal Power Plant as per MOEF&CC… — lapsed, 1.2 km away
- Proposed Expansion by addition of 2 x 660 MW Supercritical Units of… — environmental approval granted, 1.2 km away
- Proposed Expansion by addition of 2 x 660 MW Supercritical Units of… — cleared for impact study, 1.2 km away
- Amendment in Environment Clearance for FGD exemption as per MoEFCC… — lapsed, 6.3 km away
- River Bed Mining of Sand of area 4.50 hectares for proposed production… — environmental approval granted, 6.7 km away
More from Chhattisgarh State Power Generation Company Limited in Korba
- Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking… — under environmental review
- Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking… — more information requested
- 2x250MW,Thermal Power Plant at Korba (East), Chhattisgarh of M/s Chhattisgarh… — returned to applicant
- 2x250 MW , Thermal Power Plant at Korba (East), Chhattisgarh of M/s… — returned to applicant
- 2x250 MW , Thermal Power Plant, Chhattisgarh State Electricity Board (CSEB)… — withdrawn
- Proposed Expansion by addition of 2 x 660 MW Supercritical Units of… — more information requested
16 Chhattisgarh State Power projects in Korba
All 30 Chhattisgarh State Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.