| Forest Diversion Proposal over 20.950Ac./8.478Ha. Forest Land for the construction of… Hirama, Jharsuguda, Odisha | Buildings & townships | 21 acres | Under forest review | 16 Oct 2026 |
| Talabira II & III Opencast Coal Mine Patrapali, Jharsuguda, Odisha | Mining | 4,729.7 acres | Environmental approval granted | 28 Aug 2026 |
| Talabira II & III Open Cast Mine Rampur, Jharsuguda, Odisha | Mining | 4,729.7 acres | Returned to applicant | 18 Jul 2026 |
| Machhakata (Revised) Opencast Coal Mine Bagdia, Anugul, Odisha | Mining | 5,852.3 acres | Lapsed | 12 Jun 2026 |
| New Patrapara South Opencast Coal Mine Bagdia, Anugul, Odisha | Mining | 3,249.4 acres | More information requested | 30 May 2026 |
| New Patrapara South Opencast Coal Mine Bagdia, Anugul, Odisha | Mining | 3,249.4 acres | Not approved | 26 May 2026 |
| Machhakata (Revised) Opencast Coal Mine Bagdia, Anugul, Odisha | Mining | 5,852.3 acres | Not approved | 21 May 2026 |
| Rehabilitation & Resettelment Colony and its connecting Road of Talabira II & III OCP of… Khinda, Sambalpur, Odisha | Roads & highways | 48.2 acres | Lapsed | 10 Mar 2026 |
| New Patrapara South Opencast Coal Mine Similipal, Anugul, Odisha | Mining | 3,249.4 acres | Lapsed | 4 Mar 2026 |
| New Patrapara South Opencast Coal Mine Similipal, Anugul, Odisha | Mining | 3,249.4 acres | Not approved | 2 Mar 2026 |
| Expansion of 2x660MW Super Critical Lignite based Thermal Power Project by NLC India Ltd Kunankurichchi, Cuddalore, Tamil Nadu | Power | 607.3 acres | Returned to applicant | 7 Jun 2025 |
| Environmental Clearance (EC) for the proposed establishment of the Integrated Township,… Lapanga, Sambalpur, Odisha | Buildings & townships | 117.1 acres | Environmental approval granted | 10 May 2025 |
| 1X800MW NLC Talabira Thermal Power Project (NTTPP) Phase-II Hirama, Jharsuguda, Odisha | Power | 461.7 acres | Cleared for impact study | 30 Oct 2024 |
| Neyveli New Thermal Power Station (2x500 MW) Neyveli (Ts), Cuddalore, Tamil Nadu | Power | 395.4 acres | Environmental approval granted | 14 Jun 2024 |
Nlc India projects by city
Where Nlc India is building
Questions people ask
How many projects has Nlc India filed?
14 since January 2022, of which 4 are approved and 4 are awaiting a decision.
Where are Nlc India's projects?
Mostly in Anugul, Odisha (6), Jharsuguda, Odisha (4), Sambalpur, Odisha (2) and Cuddalore, Tamil Nadu (2).
What did Nlc India file most recently?
Forest Diversion Proposal over 20.950Ac./8.478Ha. Forest Land for the construction of Rehabilitation and Resettlement (R&R) colony for Project Displaced Families (PDFs) of Talabira NLC Thermal Power Project (NTTPP) in fovour of NLC India Limited in Hirama, Jharsuguda, filed on 16 Oct 2026. Status: Under forest review.
About this information
Compiled from publicly available approval records, grouped by the applicant's registered name. What is Developing? is not affiliated with Nlc India; the logo is shown only to identify the company. Group companies that file under different names may appear on separate pages. Statuses can change between our updates; check with the authority before making decisions. Spotted a mistake? Tell us.