| Status | Projects |
|---|---|
| Filed or under review | 2 |
| Approved | 1 |
| Withdrawn or lapsed | 1 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| TNPDCL-RDSS-New 11kV Adari Feeder Pole and Line Erection work Kattumavilur, Veppur | Power | 47.5 acres | Lapsed | 7 Aug 2025 |
| Expansion of 2x660MW Super Critical Lignite based Thermal Power Project by NLC India Ltd Kunankurichchi, Virudhachalam | Power | 607.3 acres | Returned to applicant | 7 Jun 2025 |
| Laying of OFC through TNEB poles (Existing-26 no's), in the Reserve Forest of Semakottai… Semakottai Rf, Virudhachalam | Power | 0.1 acres | More information requested | 11 Mar 2025 |
| Neyveli New Thermal Power Station (2x500 MW) Neyveli (Ts), Kurinjipadi | Power | 395.4 acres | Environmental approval granted | 14 Jun 2024 |
Questions people ask
How many power projects are planned in Cuddalore?
4 power projects in Cuddalore have applied for approval since January 2022. 3 of them are active (not withdrawn, lapsed or rejected) and 2 are still awaiting a decision.
What was approved most recently in Cuddalore?
Neyveli New Thermal Power Station (2x500 MW) in Neyveli (Ts) — “Environmental approval granted” on 18 Jun 2025.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.