Quick answers
What is SEIL Energy India Limited Project-2?
SEIL Energy India Limited Project-2 is an approved power project in Eduru, Thotapalligudur, Nellore, Andhra Pradesh. The site covers 988.4 acres.
Who is building it?
The applicant is Sembcorp Energy India Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 7 Oct 2024), as of 27 Nov 2026.
Where is it?
In Eduru, Thotapalligudur, Nellore, Andhra Pradesh.
How big is it?
It has a stated cost of ₹9,755 crore and a site of 988.4 acres.
When was it filed?
The application was filed on 22 Aug 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 7 Oct 2024 |
| Application filed | 22 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Power |
| Applicant | Sembcorp Energy India Limited |
| Land area | 988.4 acres (400 ha) |
| Project cost | ₹9,755 crore |
| Village / locality | Eduru |
| Taluk / tehsil | Thotapalligudur |
| District | Sri Potti Sriramulu Nellore (Nellore) |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-01842 |
In context
7 applications in Nellore since January 2022 are in the same category (Power): 4 approved, 1 filed or under review, and 2 withdrawn, lapsed or rejected.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Eduru, Thotapalligudur, Nellore, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Power project by SEIL Energy India Limited — environmental approval granted, 2.2 km away
- CRZ Clearance for Fishing Jetty and Landing Centre at Nelaturu, Muthukuru… — coastal clearance granted, 3.4 km away
- Sri Damodaram Sanjeevaiah Thermal Power Station (SDSTPS) Stage-I (2x800 MW) &… — returned to applicant, 3.5 km away
- Building project by M/s. 3F INDUSTRIES LIMITED — under environmental review, 14.1 km away
- NEW INDUSTRIAL SHED FOR REFINING, PROCESSING, MANUFACTURING, PACKAGING… — environmental approval granted, 15.7 km away
- Residential Apartment Building Construction Project - DSR Infrastructure… — environmental approval granted, 18.8 km away
- Hotel Building construction project at Survey Nos. 1189 and 1190/4, Nellore… — environmental approval granted, 18.9 km away
- Industrial project by M/s. Transworld Furtichem Limited — environmental approval granted, 19.7 km away
More from Sembcorp Energy India Limited in Sri Potti Sriramulu Nellore
- Power project by SEIL Energy India Limited — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.