What is Road From Chintapalli to Urrinka of Buttayagudem Mandal?
Road From Chintapalli to Urrinka of Buttayagudem Mandal is a proposed road project in Orinka, Buttayagudem, Eluru, Andhra Pradesh. The site covers 9.2 acres.
Who is building it?
The applicant is Executive Engineer, PR Division, Janagreddygudem.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Orinka, Buttayagudem, Eluru, Andhra Pradesh.
How big is it?
It has a stated cost of ₹4.8 crore; a site of 9.2 acres and 5.9 acres (2.4 ha) of forest land.
When was it filed?
The application was filed on 22 Sept 2026.
Project details
| Official title | Road From Chintapalli to Urrinka of Buttayagudem Mandal in Eluru District |
|---|---|
| Status | More information requested |
| Status since | 23 Nov 2026 |
| Application filed | 22 Sept 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Executive Engineer, PR Division, Janagreddygudem |
| Land area | 9.2 acres (3.7 ha) |
| Forest land | 5.9 acres (2.4 ha) |
| Project cost | ₹4.8 crore |
| Village / locality | Orinka |
| Taluk / tehsil | Buttayagudem |
| District | Eluru |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-04952 |
In context
10 applications in Eluru since January 2022 are in the same category (Roads & highways): 0 approved, 8 filed or under review, and 2 withdrawn, lapsed or rejected. At 9.2 acres, this one is larger than 70% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Orinka, Buttayagudem, Eluru, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Laying underground OFC along the roads between "Koyyalgudem-Kannapuram-Gogumill… — more information requested, 2.2 km away
- Laying underground OFC along the roads between "Koyyalgudem-Kannapuram-Gogumill… — forest land use approved, 2.2 km away
- Bsnl 4g Saturation Project_ginnepalli_eluru_ap — under wildlife review, 5.5 km away
- Bsnl 4g Saturation Project_dharwada_eluru_ap — lapsed, 7 km away
- Bsnl 4g Saturation Project_dharwada_eluru_ap — decision issued, 7 km away
- Road from KP Road to Veerannapalem — in-principle approval, conditions pending, 7.3 km away
- Diversion of 0.04 Ha of Forest Land for Construction of Mobile Tower for… — under wildlife review, 7.5 km away
- Diversion of 0.04 Ha of Forest Land for Construction of Mobile Tower for… — lapsed, 7.5 km away
More from Executive Engineer, PR Division, Janagreddygudem in Eluru
- Road from KP Road to Veerannapalem — in-principle approval, conditions pending
- Road from LND Peta to Gummuluru of Buttayagudem mandal — in-principle approval, conditions pending
- Road from Gurugumilli to Puchiokagondi via Chintakonda, Gottalarevu — in-principle approval, conditions pending
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.