What is 2x195 MW (Stage-ll) Coal Based Thermal Power Plant by NTPC?
2x195 MW (Stage-ll) Coal Based Thermal Power Plant by NTPC is a lapsed power project in Senduari Gaj Singh, Baruraj (Motipur), Muzaffarpur, Bihar. The site covers 1,237.7 acres.
Who is building it?
The applicant is NTPC Limited (NTPC).
Has it been approved?
No. The application was lapsed on 24 Aug 2026, so it is no longer under consideration.
Where is it?
In Senduari Gaj Singh, Baruraj (Motipur), Muzaffarpur, Bihar.
How big is it?
It has a stated cost of ₹4,778.7 crore and a site of 1,237.7 acres.
When was it filed?
The application was filed on 22 Dec 2025.
Project details
| Official title | 2x195 MW (Stage-ll) Coal Based Thermal Power Plant at village Kanti, in Muzaffarpur Distt. in Bihar |
|---|---|
| Status | Lapsed |
| Status since | 24 Aug 2026 |
| Application filed | 22 Dec 2025 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Power |
| Applicant | NTPC Limited (NTPC) |
| Land area | 1,237.7 acres (500.9 ha) |
| Project cost | ₹4,778.7 crore |
| Village / locality | Senduari Gaj Singh |
| Taluk / tehsil | Baruraj (Motipur) |
| District | Muzaffarpur |
| State | Bihar |
| Location from | Site boundary on record |
| Our reference | WID-BR-01216 |
In context
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Senduari Gaj Singh, Baruraj (Motipur), Muzaffarpur, Bihar. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- M/s Muzaffarpur Thermal Power Station, 2X195 MW(Stage-II) Coal Based Thermal… — environmental approval granted, 50 m away
- M/s Muzaffarpur Thermal Power Station, 2X195 MW(Stage-II) Coal Based Thermal… — withdrawn, 50 m away
- Proposed 50 TPH PPC/OPC Cement Grinding Unit based on Closed-Circuit Ball Mill… — under environmental review, 2.8 km away
- Industrial project by Maa Bhagwati Sponge Iron PVT. LTD. — cleared for impact study, 3 km away
- Brick Earth Mining Project of M/s Shakti Bricks — environmental approval granted, 5.4 km away
- Sand Mining Project on Sand Ghat/ Unit No.-08 (Kharar Ghat-03) on Burhi Gandak… — environmental approval granted, 5.9 km away
- Sand Mining Project on Sand Ghat/ Unit No.-08 (Kharar Ghat-03) on Burhi Gandak… — cleared for impact study, 5.9 km away
- Sand Ghat/Unit No.- 04 (Ghosaut Sand Ghat-01A) on Burhi Gandak river of… — cleared for impact study, 6.1 km away
More from NTPC Limited (NTPC) in Muzaffarpur
- M/s Muzaffarpur Thermal Power Station, 2X195 MW(Stage-II) Coal Based Thermal… — environmental approval granted
- M/s Muzaffarpur Thermal Power Station, 2X195 MW(Stage-II) Coal Based Thermal… — withdrawn
3 NTPC projects in Muzaffarpur
All 129 NTPC projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.