What is this project?
Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500 TPA), WHRB based Power Plant from 4 MW to 34 MW, FBC based Power Plant from 4 MW to 24 MW, Induction Furnaces is a proposed industrial project in Delari, Raigarh, Chhattisgarh. The site covers 154.8 acres.
Who is building it?
The applicant is Maa Kali Alloys Udyog Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 22 Apr 2024), as of 27 Nov 2026.
Where is it?
In Delari, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹544 crore and a site of 154.8 acres.
When was it filed?
The application was filed on 24 Nov 2023.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500 TPA), WHRB…
Project details
| Official title | Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500 TPA), WHRB based Power Plant from 4 MW to 34 MW, FBC based Power Plant from 4 MW to 24 MW, Induction Furnaces along with CCM & LRF (Hot Billets / MS Billets / Ingots from 56,000 TPA to 3,72,800 TPA), New Rolling Mill (Rolled Product) – 3,96,000 TPA, Coal Gasifier for Reheating Furnace – 3,500 NM3/Hr., New Ferro Alloys Unit (2 x 9 MVA) to produce FeSi - 14,000 TPA / FeMn - 50,400 TPA / SiMn -28,800 TPA / FeCr - 30,000 |
|---|---|
| Status | Cleared for impact study |
| Status since | 22 Apr 2024 |
| Application filed | 24 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Maa Kali Alloys Udyog Private Limited |
| Land area | 154.8 acres (62.7 ha) |
| Project cost | ₹544 crore |
| Village / locality | Delari |
| Taluk / tehsil | Raigarh |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00397 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 4 Apr 2025 | Environmental approval granted | 154.8 acres | ₹544 crore |
| Early planning filed 24 Nov 2023 (this page) | Cleared for impact study | 154.8 acres | ₹544 crore |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 154.8 acres, this one is larger than 66% of them.
49 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Delari, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500… — environmental approval granted, 0 m away
- 2 X 95 Tpd Dri Kilns to Manufacture 62,700 Tpa of Sponge Iron, 2 X 3.0 MW of… — environmental approval granted, 350 m away
- Change in name from S S Steel & Power to S.S. STEELS & POWER PRIVATE LIMITED… — lapsed, 850 m away
- Approach Road — lapsed, 950 m away
- Approach Road — lapsed, 950 m away
- Amendment in Environment Clearance obtained for Establishment of 2 x 95 TPD… — lapsed, 1.3 km away
- Transfer of Environment Clearance (EC) of M/s. Vinayaka Iron & Steel… — environmental approval granted, 1.3 km away
- 132KV Transmission Line from CSPTCL 220/132/33 KV Substation Gerwani to M/s… — lapsed, 1.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.