What is this project?
2 X 95 Tpd Dri Kilns to Manufacture 62,700 Tpa of Sponge Iron, 2 X 3.0 MW of Whrb Based Power Plant &8.0 MW Fbc Based Power Plant is an approved industrial project in Pali, Raigarh, Chhattisgarh. The site covers 50.8 acres.
Who is building it?
The applicant is Vinayaka Iron & Steel Industries..
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 5 Jun 2023), as of 27 Nov 2026.
Where is it?
In Pali, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹110 crore and a site of 50.8 acres.
When was it filed?
The application was filed on 5 Jun 2023.
Project details
| Official title | Establishment of 2 X 95 Tpd Dri Kilns to Manufacture 62,700 Tpa of Sponge Iron, 2 X 3.0 MW of Whrb Based Power Plant &8.0 MW Fbc Based Power Plant |
|---|---|
| Status | Environmental approval granted |
| Status since | 5 Jun 2023 |
| Application filed | 5 Jun 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Vinayaka Iron & Steel Industries. |
| Land area | 50.8 acres (20.6 ha) |
| Project cost | ₹110 crore |
| Village / locality | Pali |
| Taluk / tehsil | Raigarh |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00423 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 50.8 acres, this one is smaller than 58% of them.
47 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Pali, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500… — environmental approval granted, 350 m away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000 TPA to 4,06,500… — cleared for impact study, 350 m away
- Change in name from S S Steel & Power to S.S. STEELS & POWER PRIVATE LIMITED… — lapsed, 500 m away
- Approach Road — lapsed, 750 m away
- Approach Road — lapsed, 750 m away
- Amendment in Environment Clearance obtained for Establishment of 2 x 95 TPD… — lapsed, 1000 m away
- Transfer of Environment Clearance (EC) of M/s. Vinayaka Iron & Steel… — environmental approval granted, 1000 m away
- Proposed Change in Induction Furnaces Configuration From 3 X 15 T As Per Ec to… — initial checks, 1.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.