What is Developing? Open the mapMap

Power projects in Korba, Chhattisgarh

27 power projects in Korba district, Chhattisgarh, have applied for environmental, forest, wildlife or coastal approval since January 2022. 11 are still filed or under review, and 1 were filed in the last 30 days. Updated 27 Nov 2026.

Explore Korba on the live map

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

27power projects
11filed or under review
1filed in the last 30 days

Where they are in the approval process

StatusProjects
Filed or under review8
In-principle approval3
Approved10
Withdrawn or lapsed6

Recently approved

ProjectTypeSizeStatusFiled
Expansion of the 2x300 MW (Phase-I, Operational) and 2x660 MW (Phase-II, under…
Dhandhani, Kartala
Power1,249.3 acresEnvironmental approval granted5 May 2026
Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State…
Birbhat, Katghora
Power1,744.5 acresEnvironmental approval granted7 Oct 2024
Diversion of forest land For Non-forest Purpose under "Van (Sanrakshan) Adhiniyam 1980…
Mohora, Poundi-Uproda
Power3.5 acresForest land use approved24 Sept 2025
Expansion of the 2x300 MW (Phase-I, Operational) and 2x660 MW (Phase-II, under…
Dhandhani, Kartala
Power1,249.3 acresCleared for impact study30 Oct 2025
Revival of Environment Clearance (as more than 75% of TPP construction activities have…
Saragbundlya, Kartala
Power1,249.3 acresEnvironmental approval granted4 Sept 2025
Revival of Environment Clearance (as more than 75% of TPP construction activities have…
Dhandhani, Kartala
Power1,249.3 acresEnvironmental approval granted2 Jun 2025
Revival of Environment Clearance (as more than 75% of TPP construction activities have…
Paladi, Korba
Power1,249.3 acresCleared for impact study11 Feb 2025
KORBA POWER LIMITED Proposed for Transfer of EC (Change in Name) from Lanco Amarkantak…
Patadhi, Korba
Power635.6 acresEnvironmental approval granted4 Dec 2024
1 x 500 MW Coal Based Power Plant of M/s Chhattisgarh State Power Generation Company…
Darri, Katghora
Power670.3 acresEnvironmental approval granted14 Jun 2023
Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State…
Birbhat, Katghora
Power1,744.5 acresCleared for impact study9 Feb 2023

Recently filed

ProjectTypeSizeStatusFiled
Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking Exemption…
Darri, Katghora
Power1,744.5 acresUnder environmental review16 Nov 2026
Cumulative Addendum Environmental Impact Assessment (EIA) Report for seeking Exemption…
Darri, Katghora
Power1,744.5 acresMore information requested26 Oct 2026
2x250MW,Thermal Power Plant at Korba (East), Chhattisgarh of M/s Chhattisgarh State…
Korba, Korba
Power155 acresReturned to applicant23 Sept 2026
2x250 MW , Thermal Power Plant at Korba (East), Chhattisgarh of M/s Chhattisgarh State…
Korba, Korba
Power155 acresReturned to applicant31 Aug 2026
2x250 MW , Thermal Power Plant, Chhattisgarh State Electricity Board (CSEB) Korba East
Korba, Korba
Power155 acresWithdrawn27 Aug 2026
33KV Transmission Line for Vijay Central (Underground) Coal Mine of M/S Rungta Sons…
Beejadand, Poundi-Uproda
Power1,457.3 acresMore information requested14 Jul 2026
Amendment in Environment Clearance for FGD exemption as per MoEFCC notification, G.S.R.…
Risda, Korba
Power619.4 acresLapsed10 Jul 2026
Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State…
Jhabu, Katghora
Power1,744.5 acresMore information requested29 May 2026
New 220 KV Dcds Line Between 765/400/220 KV Dharamjaigarh (Pgcil) Substation & 220/132…
Syah\Muri, Katghora
Power2,033.1 acresUnder forest review5 May 2026
Expansion of the 2x300 MW (Phase-I, Operational) and 2x660 MW (Phase-II, under…
Dhandhani, Kartala
Power1,249.3 acresEnvironmental approval granted5 May 2026
Amendment of 2x250 MW coal based Thermal Power Plant as per MOEF&CC notification dated…
Korba, Korba
Power155 acresLapsed9 Mar 2026
Dr. Shyama Prasad Mukharji Thermal Power Station, M/s Chhattisgarh State Power…
Korba, Korba
Power41.5 acresLapsed19 Feb 2026
Amendment of 1x500 MW coal based Thermal Power Plant as per MOEF&CC notification dated…
Jhabu, Katghora
Power1,744.5 acresLapsed5 Feb 2026
Expansion of the 2x300 MW (Phase-I, Operational) and 2x660 MW (Phase-II, under…
Dhandhani, Kartala
Power1,249.3 acresCleared for impact study30 Oct 2025
Diversion of forest land For Non-forest Purpose under "Van (Sanrakshan) Adhiniyam 1980…
Mohora, Poundi-Uproda
Power3.5 acresForest land use approved24 Sept 2025
Revival of Environment Clearance (as more than 75% of TPP construction activities have…
Saragbundlya, Kartala
Power1,249.3 acresEnvironmental approval granted4 Sept 2025
Revival of Environment Clearance (as more than 75% of TPP construction activities have…
Dhandhani, Kartala
Power1,249.3 acresEnvironmental approval granted2 Jun 2025
Revival of Environment Clearance (as more than 75% of TPP construction activities have…
Paladi, Korba
Power1,249.3 acresCleared for impact study11 Feb 2025
Power project by M/S Essar Power Transmission Co. LTD- Modification of 400 KV D/C Mahan…
Sasin, Katghora -1
Power69.5 acresLapsed17 Dec 2024
KORBA POWER LIMITED Proposed for Transfer of EC (Change in Name) from Lanco Amarkantak…
Patadhi, Korba
Power635.6 acresEnvironmental approval granted4 Dec 2024
Korba Super Thermal Power Station
Ghamata, Katghora
Power248.6 acresUnder wildlife review11 Nov 2024
Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State…
Birbhat, Katghora
Power1,744.5 acresEnvironmental approval granted7 Oct 2024
Proposed 132/33 KV Substation Chotiya (Distirct - Korba)
Pondi, Poundi-Uproda
Power38.3 acresIn-principle approval, conditions pending3 Jan 2024
220 KV DCDS line from 220/132 KV Substation Chhuri to M/s SECL Gevra area - I & II…
Jamn\Mura, Katghora
Power979.7 acresIn-principle approval, conditions pending1 Nov 2023
1 x 500 MW Coal Based Power Plant of M/s Chhattisgarh State Power Generation Company…
Darri, Katghora
Power670.3 acresEnvironmental approval granted14 Jun 2023
Power project by M/S Essar Power Transmission Co. LTD- Modification of 400 KV D/C Mahan…
Sasin, Katghora -1
Power480.4 acresIn-principle approval, conditions pending28 Mar 2023
Proposed Expansion by addition of 2 x 660 MW Supercritical Units of Chhattisgarh State…
Birbhat, Katghora
Power1,744.5 acresCleared for impact study9 Feb 2023

Questions people ask

How many power projects are planned in Korba?

27 power projects in Korba have applied for approval since January 2022. 21 of them are active (not withdrawn, lapsed or rejected) and 11 are still awaiting a decision.

What was approved most recently in Korba?

Expansion of the 2x300 MW (Phase-I, Operational) and 2x660 MW (Phase-II, under construction) Proposed with capacity of 2x800MW (1600 MW, under Phase-III Ultra Super Critical TPP) within the existing Plant area by Korba Power Limited in Dhandhani — “Environmental approval granted” on 19 Jun 2026.

How often is this list updated?

Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.

Most active developers in Korba

Other districts in Chhattisgarh