Environmental approval grantedIndustry · Baloda Bazar, Chhattisgarh

Greenfield Project for Production Facilities of Pelletization Plant (0.60 MTPA), DRI Plant (0.42 MTPA), SMS with Caster (0.25 MTPA), Captive Power Plant of 85 MW (WHRB#32 MW & Coal & Dolochar based#53 MW), Rolling Mill (0.20 MTPA), Pig Iron (0.26 MTPA), Sinter Plant (0.40 MTPA), DIP Plant (0.24 MTPA), PGP of 8000 Nm3/hr & Coal Washery Unit (0.98 MTPA)" by M/s Swadesh Metallics Pvt Ltd

Greenfield Project for Production Facilities of Pelletization Plant (0.60 MTPA), DRI Plant (0.42 MTPA), SMS with Caster (0.25 MTPA), Captive Power Plant of 85 MW (WHRB#32 MW & Coal & Dolochar based#53 MW), Rolling Mill (0.20 MTPA), Pig Iron (0.26 MTPA), Sinter Plant (0.40 MTPA), DIP Plant (0.24 MTPA), PGP of 8000 Nm3/hr & Coal Washery Unit (0.98 MTPA)" by M/s Swadesh Metallics Pvt Ltd is an approved industrial project in Kesda, Simga, Baloda Bazar, Chhattisgarh. The site covers 510.9 acres. Its stated project cost is ₹1,221 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 2 Jan 2024).

See it on the live map All projects in Baloda Bazar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleGreenfield Project for Production Facilities of Pelletization Plant (0.60 MTPA), DRI Plant (0.42 MTPA), SMS with Caster (0.25 MTPA), Captive Power Plant of 85 MW (WHRB#32 MW & Coal & Dolochar based#53 MW), Rolling Mill (0.20 MTPA), Pig Iron (0.26 MTPA), Sinter Plant (0.40 MTPA), DIP Plant (0.24 MTPA), PGP of 8000 Nm3/hr & Coal Washery Unit (0.98 MTPA)" at Village-Kesda, Tehsil-Simga, District-Balodabazar-Bhatapara-493332, Chhattisgarh by M/s Swadesh Metallics Pvt Ltd.
StatusEnvironmental approval granted
Status since2 Jan 2024
Application filed15 Jun 2023
Approval soughtEnvironmental approval
Application typeNew project
SectorIndustry
ApplicantM/S Swadesh Metallics PVT LTD
Land area510.9 acres (206.8 ha)
Project cost₹1,221 crore
Village / localityKesda
Taluk / tehsilSimga
DistrictBaloda Bazar
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-00594

In context

31 applications in Baloda Bazar since January 2022 are in the same category (Industry): 21 approved, 7 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 510.9 acres, this one is larger than 68% of them.

4 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Kesda, Simga, Baloda Bazar, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.