31industry projects
7filed or under review
2filed in the last 30 days

Where they are in the approval process

StatusProjects
Filed or under review7
Approved21
Withdrawn or lapsed3

Recently approved

ProjectTypeSizeStatusFiled
Change in Project Configuration Under Clause 7(Ii):kiln-1 Reduced From 4.5 to 2.6 Mtpa,…
Khapradih, Simga
Industry393.5 acresEnvironmental approval granted18 Aug 2026
Greenfield Cement Clinkerisation Plant (4.5 MTPA), Grinding Unit (1.0 MTPA), CFBC/AFBC…
Khaira, Bhatapara
Industry703.6 acresCleared for impact study28 Oct 2026
Request for Amendment to Environmental Clearance (EC) for permission for utilisation of…
Ghughuwadih (Ghughwadih, Simga
Industry54.7 acresEnvironmental approval granted3 Jun 2026
Greenfield project of Sponge Iron (350 TPD X 4 Nos.) 490000 TPA, MS Billets (IF 25 MT X…
Majhgaon, Bhatapara
Industry413.3 acresCleared for impact study12 Feb 2026
Transfer of Environment Clearance from M/s. SAMBHV TUBES PRIVATE LIMITED to SAMBHV STEEL…
Kesda, Simga
Industry101.9 acresEnvironmental approval granted19 Dec 2025
Expansion of existing Cold Rolling Mill Capacity from 28,000 TPA to 1,150,000 TPA
Ringni, Simga
Industry763.7 acresCleared for impact study5 Aug 2025
Greenfield steel project of DRI based Sponge Iron 700000 TPA I/O Pellets 1200000 TPA PGP…
Kesda, Simga
Industry101.9 acresEnvironmental approval granted24 Sept 2025
Amendment in Environmental Clearance Condition issued to Lala Pipes Private Limited
Puisari, Simga
Industry36.8 acresEnvironmental approval granted19 Jun 2025
Application for Amendment to TOR letter issued to M/s. Max Steel and Power Pvt. Ltd.…
Mohbhata, Simga
Industry73.4 acresCleared for impact study3 Mar 2025
Transfer of Environment Clearance vide no. J-11011/420/2017-IA.II(I) dated 29th January…
Khajri, Baloda Bazar
Industry18.9 acresEnvironmental approval granted20 Jan 2025

Recently filed

ProjectTypeSizeStatusFiled
Industrial project by M/s. R.S. Infraprojects Limited
Kesda, Simga
Industry61.8 acresInitial checks16 Nov 2026
Greenfield Cement Clinkerisation Plant (4.5 MTPA), Grinding Unit (1.0 MTPA), CFBC/AFBC…
Khaira, Bhatapara
Industry703.6 acresCleared for impact study28 Oct 2026
Expansion of existing Cold Rolling Mill Capacity from 28,000 TPA to 1,150,000 TPA
Ringni, Simga
Industry763.7 acresUnder environmental review15 Oct 2026
Amendment in Existing Environmental Clearance Letter granted vide F. No.…
Semaradih, Baloda Bazar
Industry548.6 acresUnder environmental review7 Sept 2026
Amendment in Existing Environmental Clearance letter granted vide F. No.…
Chhirahi, Palari
Industry959.7 acresUnder environmental review7 Sept 2026
Expansion of Integrated Cement (Clinker: 8.1 MTPA to 16.1 MTPA, Cement: 6.5 MTPA to 16.5…
Rawan, Baloda Bazar
Industry590.5 acresLapsed27 Aug 2026
Change in Project Configuration Under Clause 7(Ii):kiln-1 Reduced From 4.5 to 2.6 Mtpa,…
Khapradih, Simga
Industry393.5 acresEnvironmental approval granted18 Aug 2026
Request for Amendment to Environmental Clearance (EC) for permission for utilisation of…
Ghughuwadih (Ghughwadih, Simga
Industry54.7 acresEnvironmental approval granted3 Jun 2026
Greenfield project of Sponge Iron (350 TPD X 4 Nos.) 490000 TPA, MS Billets (IF 25 MT X…
Majhgaon, Bhatapara
Industry413.3 acresCleared for impact study12 Feb 2026
Transfer of Environment Clearance from M/s. SAMBHV TUBES PRIVATE LIMITED to SAMBHV STEEL…
Kesda, Simga
Industry101.9 acresEnvironmental approval granted19 Dec 2025
Greenfield steel project of DRI based Sponge Iron 700000 TPA I/O Pellets 1200000 TPA PGP…
Kesda, Simga
Industry101.9 acresEnvironmental approval granted24 Sept 2025
Expansion of existing Cold Rolling Mill Capacity from 28,000 TPA to 1,150,000 TPA
Ringni, Simga
Industry763.7 acresCleared for impact study5 Aug 2025
Amendment in Environmental Clearance Condition issued to Lala Pipes Private Limited
Puisari, Simga
Industry36.8 acresEnvironmental approval granted19 Jun 2025
Application for Amendment to TOR letter issued to M/s. Max Steel and Power Pvt. Ltd.…
Mohbhata, Simga
Industry73.4 acresCleared for impact study3 Mar 2025
Transfer of Environment Clearance vide no. J-11011/420/2017-IA.II(I) dated 29th January…
Khajri, Baloda Bazar
Industry18.9 acresEnvironmental approval granted20 Jan 2025
Greenfield steel project of DRI based Sponge Iron 700000 TPA I/O Pellets 1200000 TPA PGP…
Kesda, Simga
Industry101.9 acresCleared for impact study26 Nov 2024
Greenfield Steel Plant comprising of DRI Kilns (Sponge Iron - 3,63,000 TPA), Induction…
Kukrachunda (Siabandha), Simga
Industry265.1 acresCleared for impact study2 Nov 2024
Amendment in extension in validity letter dated 24th Jan., 2022 of existing EC letter…
Hirmi, Simga
Industry412.9 acresLapsed9 Oct 2024
Amendment in Ec Pertaining to Reduction in Extent of Land From 9.949 Ha. to 7.661 Ha.…
Khajri, Baloda Bazar
Industry18.9 acresEnvironmental approval granted6 Oct 2024
Splitting of EC granted to M/s. Animesh Ispat Pvt. Ltd. vide order no. F. No.…
Khajri, Baloda Bazar
Industry24.6 acresReturned to applicant17 Aug 2024
Expansion of Integrated Cement (Clinker: 8.1 MTPA to 16.1 MTPA, Cement: 6.5 MTPA to 16.5…
Rawan, Baloda Bazar
Industry590.5 acresCleared for impact study11 May 2024
DRI Kilns (Sponge Iron – 6,27,000 TPA), Induction Furnaces with LRF + CCM (Billets /…
Ghughuwadih (Ghughwadih, Simga
Industry176.6 acresEnvironmental approval granted25 Dec 2023
DRI Kilns (Sponge Iron – 6,27,000 TPA), Induction Furnaces with LRF + CCM (Billets /…
Ghughuwadih (Ghughwadih, Simga
Industry176.6 acresWithdrawn9 Dec 2023
I/O Beneficiation-1.5 MTPA (throughput),Pellet Plant-0.8 MTPA,DRI Kilns-2x600 TPD…
Mohbhata, Simga
Industry661.4 acresEnvironmental approval granted1 Dec 2023
Proposed Steel Plant- Iron ore beneficiation(Beneficiated iron ore–1.3 MTPA),Pellet…
Kesda, Simga
Industry241.9 acresEnvironmental approval granted21 Sept 2023
Amendment to Terms of Reference ( ToR) issued to M/s GOS ISPAT PRIVATE LIMITED for the…
Ghughuwadih (Ghughwadih, Simga
Industry54.7 acresCleared for impact study9 Sept 2023
Regularization project for 28000 TPA Cold Rolling Mill (Thickness Reduction process) by…
Kesda, Simga
Industry145.1 acresMore information requested31 Jul 2023
Greenfield project comprising of Establishment of DRI Kilns (2,31,000 TPA), Induction…
Puisari, Simga
Industry36.8 acresEnvironmental approval granted17 Jul 2023
I/O Beneficiation-1.5 MTPA (throughput),Pellet Plant-0.8 MTPA,DRI Kilns-2x600 TPD…
Mohbhata, Simga
Industry430.3 acresCleared for impact study10 Jul 2023
Greenfield Project for Production Facilities of Pelletization Plant (0.60 MTPA), DRI…
Kesda, Simga
Industry510.9 acresEnvironmental approval granted15 Jun 2023
I/O Beneficiation-1.5 MTPA (throughput),Pellet Plant-0.8 MTPA,DRI Kilns-2x600 TPD…
Mohbhata, Simga
Industry661.4 acresReturned to applicant7 Jun 2023

Questions people ask

How many industry projects are planned in Baloda Bazar?

31 industry projects in Baloda Bazar have applied for approval since January 2022. 28 of them are active (not withdrawn, lapsed or rejected) and 7 are still awaiting a decision.

What was approved most recently in Baloda Bazar?

Change in Project Configuration Under Clause 7(Ii):kiln-1 Reduced From 4.5 to 2.6 Mtpa, Kiln-2 From 4.5 to 2.9 Mtpa, No Change in Kiln-3(4.5 Mtpa) & Installation of New Kiln-4(3.5 Mtpa) With No Change in Overall Ec Granted Clinker Capacity (13.5 Mtpa), Reduction in Cpp Capacity From 125 to 75 MW, While Cement(16.5 Mtpa), Whrs(100 MW), Sy. Gypsum Unit(65 Tph) and Dgset (2000 Kva) Remain Unchanged Within the Existing Plant at Khapradih, Simga, Dist.: Balodabazar-Bhatapara (Cg) by Shree Cement LTD. in Khapradih — “Environmental approval granted” on 25 Nov 2026.

How often is this list updated?

Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.

Most active developers in Baloda Bazar