Quick answers
What is this project?
DRI Kilns (Sponge Iron 2,31,000 TPA), Induction Furnace with LRF & CCM (MS Billets / Ingots) (2,47,500 TPA), WHRB based Power Plant – 2 x 10 MW, CFBC based Power Plant – 1 x 10.0 MW, at Kh. No 340/3,340/5,341,342,351/2, 352/1, Village Bhibhauri, Tehsil -Tilda District Raipur, Chhattisgarh is a proposed industrial project in Bhimbhori, Tilda, Raipur, Chhattisgarh. The site covers 102.9 acres.
Who is building it?
The applicant is Seeta Sponge and Power Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 30 Nov 2023), as of 27 Nov 2026.
Where is it?
In Bhimbhori, Tilda, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹290 crore and a site of 102.9 acres.
When was it filed?
The application was filed on 25 Oct 2023.
Project details
| Official title | Establishment of DRI Kilns (Sponge Iron 2,31,000 TPA), Induction Furnace with LRF & CCM (MS Billets / Ingots) (2,47,500 TPA), WHRB based Power Plant – 2 x 10 MW, CFBC based Power Plant – 1 x 10.0 MW, at Kh. No 340/3,340/5,341,342,351/2, 352/1, Village Bhibhauri, Tehsil -Tilda District Raipur, Chhattisgarh. |
|---|---|
| Status | Cleared for impact study |
| Status since | 30 Nov 2023 |
| Application filed | 25 Oct 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Seeta Sponge and Power Private Limited |
| Land area | 102.9 acres (41.6 ha) |
| Project cost | ₹290 crore |
| Village / locality | Bhimbhori |
| Taluk / tehsil | Tilda |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00728 |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 102.9 acres, this one is larger than 83% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhimbhori, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- DRI Kilns (Sponge Iron 1,32,000 TPA), Induction Furnace with LRF & CCM (MS… — environmental approval granted, 1.7 km away
- DRI Kilns (Sponge Iron 1,32,000 TPA), Induction Furnace with LRF & CCM (MS… — cleared for impact study, 2.3 km away
- Proposed 120 KLPD Grain Based Distillery Plant (Ethanol) — under environmental review, 2.4 km away
- Proposed 120 KLPD Grain Based Distillery Plant (Ethanol) — under environmental review, 2.4 km away
- Proposed 120 KLPD Grain Based Distillery Plant (Ethanol) — under environmental review, 2.4 km away
- Proposed 120 KLPD Grain Based Distillery Plant (Ethanol) — initial checks, 2.4 km away
- Proposed 120 KLPD Grain Based Distillery Plant (Ethanol) — environmental approval granted, 2.4 km away
- Proposed I/O Beneficiation Plant (1x 0.7 MTPA) 7,00,000 TPA, Pellet Plant… — environmental approval granted, 3.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.