Quick answers
What is this project?
Proposed DRI Plant (Sponge Iron 135000 TPA), WHRB 10MW, AFBC Power Plant 3.5MW, Submerged Electric Arc Furnace 7 MVA(Ferro Manganese 12600 TPA), Table top furnace (Brown Fused Alumina 10500 TPA) by M/s Shri Baba Baidnath Ispat Pvt Ltd at Sy No 339/1, 339/3, 340, 341, 348/1, 348/2, 349/1, 349/2, 349/3, 349/4, 349/5, 350/1, 350/2, 350/3, 350/4, 351/1, 359/1, 351/2, 359/2, 351/3, 359/3, 352, 353, 354, 355/1, 355/2, 356, 360, 362 and 363/2, Vill.-Gaitra & Raikheda, Teh.-Tilda, Dist.-Raipur, Chhattis is an approved industrial project in Raikheda, Tilda, Raipur, Chhattisgarh. The site covers 249.4 acres.
Who is building it?
The applicant is Shri Baba Baidnath Ispat Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 13 May 2024), as of 27 Nov 2026.
Where is it?
In Raikheda, Tilda, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹75 crore and a site of 249.4 acres.
When was it filed?
The application was filed on 18 Dec 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 13 May 2024 |
| Application filed | 18 Dec 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Shri Baba Baidnath Ispat Private Limited |
| Land area | 249.4 acres (100.9 ha) |
| Project cost | ₹75 crore |
| Village / locality | Raikheda |
| Taluk / tehsil | Tilda |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00734 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 18 Dec 2023 (this page) | Environmental approval granted | 249.4 acres | ₹75 crore |
| Early planning filed 9 Feb 2023 | Cleared for impact study | 249.4 acres | ₹75 crore |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 249.4 acres, this one is larger than 93% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Raikheda, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed DRI Plant (Sponge Iron 135000 TPA), WHRB 10MW, AFBC Power Plant… — cleared for impact study, 0 m away
- Proposed I/O Beneficiation Plant (1x 0.7 MTPA) 7,00,000 TPA, Pellet Plant… — environmental approval granted, 2.1 km away
- Proposed I/O Beneficiation Plant (1x 0.7 MTPA) 7,00,000 TPA, Pellet Plant… — cleared for impact study, 2.1 km away
- DRI Kilns (Sponge Iron 1,32,000 TPA), Induction Furnace with LRF & CCM (MS… — environmental approval granted, 3.7 km away
- DRI Kilns (Sponge Iron 1,32,000 TPA), Induction Furnace with LRF & CCM (MS… — cleared for impact study, 3.8 km away
- DRI Kilns (Sponge Iron 2,31,000 TPA), Induction Furnace with LRF & CCM (MS… — cleared for impact study, 5.3 km away
- Proposed 120 KLPD Grain Based Distillery Plant (Ethanol) — under environmental review, 6.6 km away
- Proposed 120 KLPD Grain Based Distillery Plant (Ethanol) — under environmental review, 6.6 km away
More from Shri Baba Baidnath Ispat Private Limited in Raipur
- Project by Shri Baba Baidnath Ispat Private Limited — initial checks
- Proposed I/O Beneficiation Plant (1x 0.7 MTPA) 7,00,000 TPA, Pellet Plant… — environmental approval granted
- Proposed I/O Beneficiation Plant (1x 0.7 MTPA) 7,00,000 TPA, Pellet Plant… — cleared for impact study
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.