Proposed Steel plant consisting of 4x250TPD DRI Kilns to produce Sponge Iron(330000TPA) IF(4x15T) LRF(15T) &RHF(10TPH) with CCM to produce Hot Billets/M.S Billets of 194040TPA RM to Produce Rolled products (TMT bars/Angles/Channels) 186766TPA through hot charging& RHF Coal based PGP 4000Nm3/hr Ferro Alloy plant(2X9MVA SAF) to produce 34000TPA Si-Mn/19000TPA Fe-Si/43000TPA Fe-Mn/68000TPA Pig Iron Power gen. through WHRB#24 MW & FBC#8 MW and Fly Ash Brick Plant of 54900 Bricks/day is a proposed industrial project in Barpali, Tamnar, Raigarh, Chhattisgarh. The site covers 123.9 acres.
Who is building it?
The applicant is Kelo Steel & Power Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 29 Nov 2024), as of 27 Nov 2026.
Where is it?
In Barpali, Tamnar, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹445.1 crore and a site of 123.9 acres.
When was it filed?
The application was filed on 26 Aug 2024.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed Steel plant consisting of 4x250TPD DRI Kilns to produce Sponge Iron(330000TPA)…
Project details
| Official title | Establishment of proposed Steel plant consisting of 4x250TPD DRI Kilns to produce Sponge Iron(330000TPA) IF(4x15T) LRF(15T) &RHF(10TPH) with CCM to produce Hot Billets/M.S Billets of 194040TPA RM to Produce Rolled products (TMT bars/Angles/Channels) 186766TPA through hot charging& RHF Coal based PGP 4000Nm3/hr Ferro Alloy plant(2X9MVA SAF) to produce 34000TPA Si-Mn/19000TPA Fe-Si/43000TPA Fe-Mn/68000TPA Pig Iron Power gen. through WHRB#24 MW & FBC#8 MW and Fly Ash Brick Plant of 54900 Bricks/day |
|---|---|
| Status | Cleared for impact study |
| Status since | 29 Nov 2024 |
| Application filed | 26 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Kelo Steel & Power Private Limited |
| Land area | 123.9 acres (50.2 ha) |
| Project cost | ₹445.1 crore |
| Village / locality | Barpali |
| Taluk / tehsil | Tamnar |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00950 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 20 Oct 2025 | Environmental approval granted | 123.9 acres | ₹445.1 crore |
| Early planning filed 26 Aug 2024 (this page) | Cleared for impact study | 123.9 acres | ₹445.1 crore |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 123.9 acres, this one is larger than 63% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Barpali, Tamnar, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Steel plant consisting of 4x250TPD DRI Kilns to produce Sponge… — environmental approval granted, 0 m away
- Proposed project for a DRI based Steel plant to produce Sponge Iron 132,000… — environmental approval granted, 4.5 km away
- Proposed project for a DRI based Steel plant to produce Sponge Iron 132,000… — cleared for impact study, 6.6 km away
- Greenfield Steel plant of 2x350TPD&2x200TPD DRI Kilns to produce Sponge-Fe… — returned to applicant, 13.1 km away
- Greenfield Steel plant by M/s Shubh Metallics Private Limited — cleared for impact study, 13.8 km away
- Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction… — cleared for impact study, 57.5 km away
- Environmental Clearance for establishment of I/O Beneficiation Plant (1 x 1.7… — withdrawn, 63.8 km away
- Greenfield steel plant comprising of DRI Kilns 2x350 TPD&2x200 TPD -3,63,000… — environmental approval granted, 83.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.