Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction Furnaces with matching LRF & CCM (Hot Billets / Billets - 2,97,000 TPA), Rolling Mill (Rolled Products – 3,30,000 TPA), Ferro Alloy Unit 4 x 9 MVA (FeSi – 28,000 TPA/ FeMn – 1,00,800 TPA/ SiMn – 57,600 TPA/FeCr – 60,000 TPA), Briquetting Plant (400 Kg/Hr),WHRB based Power Plant –48 MW, CFBC based Power Plant - 16 MW & Brick Manufacturing unit (76,000 Bricks / Day) is a proposed industrial project in Sivpuri, Raigarh, Chhattisgarh. The site covers 324.8 acres.
Who is building it?
The applicant is Raigarh Ispat and Power Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 18 Sept 2023), as of 27 Nov 2026.
Where is it?
In Sivpuri, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹897 crore and a site of 324.8 acres.
When was it filed?
The application was filed on 22 Jul 2023.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction Furnaces with…
Project details
| Official title | Establishment of Greenfield steel plant comprising of DRI Kilns (6,93,000 TPA), Induction Furnaces with matching LRF & CCM (Hot Billets / Billets - 2,97,000 TPA), Rolling Mill (Rolled Products – 3,30,000 TPA), Ferro Alloy Unit 4 x 9 MVA (FeSi – 28,000 TPA/ FeMn – 1,00,800 TPA/ SiMn – 57,600 TPA/FeCr – 60,000 TPA), Briquetting Plant (400 Kg/Hr),WHRB based Power Plant –48 MW, CFBC based Power Plant - 16 MW & Brick Manufacturing unit (76,000 Bricks / Day) |
|---|---|
| Status | Cleared for impact study |
| Status since | 18 Sept 2023 |
| Application filed | 22 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Raigarh Ispat and Power Private Limited |
| Land area | 324.8 acres (131.4 ha) |
| Project cost | ₹897 crore |
| Village / locality | Sivpuri |
| Taluk / tehsil | Raigarh |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00527 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 18 Dec 2024 | Environmental approval granted | 210.1 acres | ₹897 crore |
| Early planning filed 22 Jul 2023 (this page) | Cleared for impact study | 324.8 acres | ₹897 crore |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 324.8 acres, this one is larger than 81% of them.
Where it is
Sivpuri, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environmental Clearance for establishment of I/O Beneficiation Plant (1 x 1.7… — withdrawn, 20.1 km away
- Greenfield Steel plant by M/s Shubh Metallics Private Limited — cleared for impact study, 52.2 km away
- Greenfield Steel plant of 2x350TPD&2x200TPD DRI Kilns to produce Sponge-Fe… — returned to applicant, 52.6 km away
- Steel plant comprising of DRI Kilns (Sponge Iron – 1,32,000 TPA), WHRB based… — cleared for impact study, 54.3 km away
- Rakesh Ratre — environmental approval granted, 55.6 km away
- Proposed Steel plant consisting of 4x250TPD DRI Kilns to produce Sponge… — environmental approval granted, 57.5 km away
- Proposed Steel plant consisting of 4x250TPD DRI Kilns to produce Sponge… — cleared for impact study, 57.5 km away
- JIO DIGITAL FIBRE PRIVATE LIMITED, Gomarda Wild Life Sanctuary… — under forest review, 58.4 km away
More from Raigarh Ispat and Power Private Limited in Raigarh
- Amendments in Existing E.C. Issued to M/S. Raigarh Ispat PVT. LTD. Vide… — returned to applicant
- TOR amendment -Request for TOR amendment to Exempt Violation for our 90,000… — lapsed
- Expansion of Steel Plant–Sponge Iron from 1,20,000 TPA to 4,17,000 TPA, MS… — cleared for impact study
All 5 Raigarh Ispat and Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.