Cleared for impact studyIndustry · Raigarh, Chhattisgarh

Environmental Clearance for establishment steel plant comprising of I/O Beneficiation Plant (1.7MTPA), Pellet Plant (1.2MTPA), Coal Gasifier for Pellet(45000 NM3/Hr.),Sinter Plants (1.2MTPA),Coke Oven Units(0.5MTPA),Blast Furnaces(0.85MTPA),Ductile Iron Pipe Plant(0.5MTPA),Oxygen-10000 NM3/Hr., Nitrogen - 10000 NM3/Hr.,DRI Kilns(0.3465MTPA),Electric Arc Furnace(0.396MTPA),Induction Furnace(0.33MTPA),Rolling Mill(0.6MTPA),Coal Gasifier for Rolling Mill(4680 NM3/Hr.),Ferro Alloys(FeSi-0.014MTPA/FeMn-0.04MTPA,SiMn-0.028MTPA,FeCr-0.03MTPA,Pig Iron-0.048MTPA),Briquetting Plant-200Kg/Hr.,Coal Washery (0.6MTPA),WHRB Power Plant(DRI)-30MW,WHRB Power Plant (Blast Furnace)-20MW,WHRB Power (Coke Oven)-30 MW,FBC based Power Plant-20 MW,Brick Manufacturing Unit-39,600 Bricks/Day at Patarapali,Kotarliya & Siyarpali Villages, Raigarh Tehsil & District, Chhattisgarh

Environmental Clearance for establishment steel plant comprising of I/O Beneficiation Plant (1.7MTPA), Pellet Plant (1.2MTPA), Coal Gasifier for Pellet(45000 NM3/Hr.),Sinter Plants (1.2MTPA),Coke Oven Units(0.5MTPA),Blast Furnaces(0.85MTPA),Ductile Iron Pipe Plant(0.5MTPA),Oxygen-10000 NM3/Hr., Nitrogen - 10000 NM3/Hr.,DRI Kilns(0.3465MTPA),Electric Arc Furnace(0.396MTPA),Induction Furnace(0.33MTPA),Rolling Mill(0.6MTPA),Coal Gasifier for Rolling Mill(4680 NM3/Hr.),Ferro Alloys(FeSi-0.014MTPA/FeMn-0.04MTPA,SiMn-0.028MTPA,FeCr-0.03MTPA,Pig Iron-0.048MTPA),Briquetting Plant-200Kg/Hr.,Coal Washery (0.6MTPA),WHRB Power Plant(DRI)-30MW,WHRB Power Plant (Blast Furnace)-20MW,WHRB Power (Coke Oven)-30 MW,FBC based Power Plant-20 MW,Brick Manufacturing Unit-39,600 Bricks/Day at Patarapali,Kotarliya & Siyarpali Villages, Raigarh Tehsil & District, Chhattisgarh is a proposed industrial project in Patrapali, Raigarh, Chhattisgarh. The site covers 75.9 acres. Its stated project cost is ₹958 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 3 Nov 2024).

See it on the live map All projects in Raigarh

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Environmental Clearance for establishment steel plant comprising of I/O Beneficiation Plant (1.7MTPA), Pellet Plant (1.2MTPA), Coal Gasifier for Pellet(45000 NM3/Hr.),Sinter Plants (1.2MTPA),Coke Oven Units(0.5MTPA),Blast Furnaces(0.85MTPA),Ductile Iron Pipe Plant(0.5MTPA),Oxygen-10000 NM3/Hr., Nitrogen - 10000 NM3/Hr.,DRI Kilns(0.3465MTPA),Electric Arc Furnace(0.396MTPA),Induction Furnace(0.33MTPA),Rolling Mill(0.6MTPA),Coal Gasifier for Rolling Mill(4680 NM3/Hr.),Ferro Alloys(FeSi-0.014MTPA/FeMn-0.04MTPA,SiMn-0.028MTPA,FeCr-0.03MTPA,Pig Iron-0.048MTPA),Briquetting Plant-200Kg/Hr.,Coal Washery (0.6MTPA),WHRB Power Plant(DRI)-30MW,WHRB Power Plant (Blast Furnace)-20MW,WHRB Power (Coke Oven)-30 MW,FBC based Power Plant-20 MW,Brick Manufacturing Unit-39,600 Bricks/Day at Patarapali,Kotarliya & Siyarpali Villages, Raigarh Tehsil & District, Chhattisgarh is a proposed industrial project in Patrapali, Raigarh, Chhattisgarh. The site covers 75.9 acres.

Who is building it?

The applicant is Singhal Steel Private Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 3 Nov 2024), as of 27 Nov 2026.

Where is it?

In Patrapali, Raigarh, Chhattisgarh.

How big is it?

It has a stated cost of ₹958 crore and a site of 75.9 acres.

When was it filed?

The application was filed on 26 Oct 2024.

Project details

StatusCleared for impact study
Status since3 Nov 2024
Application filed26 Oct 2024
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantSinghal Steel Private Limited
Land area75.9 acres (30.7 ha)
Project cost₹958 crore
Village / localityPatrapali
Taluk / tehsilRaigarh
DistrictRaigarh
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-01629

In context

113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 75.9 acres, this one is smaller than 52% of them.

4 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Patrapali, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Singhal Steel Private Limited in Raigarh

All 4 Singhal Steel projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.