What is this project?
Environmental Clearance for establishment steel plant comprising of I/O Beneficiation Plant (1.7MTPA), Pellet Plant (1.2MTPA), Coal Gasifier for Pellet(45000 NM3/Hr.),Sinter Plants (1.2MTPA),Coke Oven Units(0.5MTPA),Blast Furnaces(0.85MTPA),Ductile Iron Pipe Plant(0.5MTPA),Oxygen-10000 NM3/Hr., Nitrogen - 10000 NM3/Hr.,DRI Kilns(0.3465MTPA),Electric Arc Furnace(0.396MTPA),Induction Furnace(0.33MTPA),Rolling Mill(0.6MTPA),Coal Gasifier for Rolling Mill(4680 NM3/Hr.),Ferro Alloys(FeSi-0.014MTPA/FeMn-0.04MTPA,SiMn-0.028MTPA,FeCr-0.03MTPA,Pig Iron-0.048MTPA),Briquetting Plant-200Kg/Hr.,Coal Washery (0.6MTPA),WHRB Power Plant(DRI)-30MW,WHRB Power Plant (Blast Furnace)-20MW,WHRB Power (Coke Oven)-30 MW,FBC based Power Plant-20 MW,Brick Manufacturing Unit-39,600 Bricks/Day at Patarapali,Kotarliya & Siyarpali Villages, Raigarh Tehsil & District, Chhattisgarh is a proposed industrial project in Patrapali, Raigarh, Chhattisgarh. The site covers 75.9 acres.
Who is building it?
The applicant is Singhal Steel Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 3 Nov 2024), as of 27 Nov 2026.
Where is it?
In Patrapali, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹958 crore and a site of 75.9 acres.
When was it filed?
The application was filed on 26 Oct 2024.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 3 Nov 2024 |
| Application filed | 26 Oct 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Singhal Steel Private Limited |
| Land area | 75.9 acres (30.7 ha) |
| Project cost | ₹958 crore |
| Village / locality | Patrapali |
| Taluk / tehsil | Raigarh |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-01629 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 75.9 acres, this one is smaller than 52% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Patrapali, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Application for Amendment to Tor Letter Issued to M/S. Singhal Steel PVT. LTD.… — under environmental review, 0 m away
- Application for Amendment to Tor Letter Issued to M/S. Singhal Steel PVT. LTD.… — cleared for impact study, 0 m away
- Manoj Kumar Agrawal — lapsed, 3.6 km away
- Proposed 2x800 MW Ultra Super Critical Coal Fired Thermal Power Project By M/s… — cleared for impact study, 4.2 km away
- Proposed 132/33 KV SUB-STATION Medical college — forest land use approved, 6 km away
- Rungta Sons Private Limited (Ferro Alloys Plant) : 2x9 MVA sub-merged arc… — environmental approval granted, 7.1 km away
- Expansion of Ferro Alloy Plant (0.03 MTPA) to Integrated Steel Plant (0.224… — cleared for impact study, 7.3 km away
- Brownfield project for expansion in DRI based Steel plant to produce Sponge… — cleared for impact study, 7.6 km away
More from Singhal Steel Private Limited in Raigarh
- Application for Amendment to Tor Letter Issued to M/S. Singhal Steel PVT. LTD.… — under environmental review
- Environmental Clearance for establishment of I/O Beneficiation Plant (1 x 1.7… — withdrawn
- Application for Amendment to Tor Letter Issued to M/S. Singhal Steel PVT. LTD.… — cleared for impact study
All 4 Singhal Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.