Quick answers
What is this project?
Shri Radhamadhav Crusher Udyog, Proprietor - Mithilesh Kumar Agrawal is a lapsed mining project in Tribhona, Pusour, Raigarh, Chhattisgarh. The site covers 4.9 acres.
Who is building it?
The applicant is Mithilesh Kumar Agrawal.
Has it been approved?
No. The application was lapsed on 3 Dec 2025, so it is no longer under consideration.
Where is it?
In Tribhona, Pusour, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹34 lakh and a site of 4.9 acres.
When was it filed?
The application was filed on 30 Nov 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 3 Dec 2025 |
| Application filed | 30 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Mithilesh Kumar Agrawal |
| Land area | 4.9 acres (2 ha) |
| Project cost | ₹34 lakh |
| Village / locality | Tribhona |
| Taluk / tehsil | Pusour |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-01746 |
In context
230 applications in Raigarh since January 2022 are in the same category (Mining): 83 approved, 47 filed or under review, and 100 withdrawn, lapsed or rejected. The approved ones took a median of 8 months from filing to approval. At 4.9 acres, this one is smaller than 62% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 8.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 2 mining leases have applied within 5 km.
Where it is
Tribhona, Pusour, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Chhotehaldi Limestone Quarry — lapsed, 500 m away
- Mining project by M/s Saurya Minerals Pvt.Ltd — environmental approval granted, 750 m away
- NTPC Limited Lara Super Thermal Power Station, Raigarh, Chhattisgarh — under forest review, 6 km away
- Expansion of Lara Super Thermal Power Project from 3200 MW [Stage-I (2x800 MW)… — more information requested, 6.3 km away
- Expansion of Lara Super Thermal Power Project from 3200 MW [Stage-I (2x800 MW)… — cleared for impact study, 6.3 km away
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — environmental approval granted, 6.3 km away
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — returned to applicant, 7.2 km away
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — environmental approval granted, 7.2 km away
About this information