NTPC Limited Lara Super Thermal Power Station, Raigarh, Chhattisgarh is a proposed industrial project in Mahloi, Pusour, Raigarh, Chhattisgarh. The site covers 3,134 acres.
Who is building it?
The applicant is NTPC Limited (NTPC).
Has it been approved?
Not yet. The application is still under review: its status is “Under forest review”, as of 27 Nov 2026.
Where is it?
In Mahloi, Pusour, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹53,899.4 crore; a site of 3,134 acres and 27 acres (10.9 ha) of forest land.
When was it filed?
The application was filed on 16 Apr 2026.
Project details
| Status | Under forest review |
|---|---|
| Status since | 19 Nov 2026 |
| Application filed | 16 Apr 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Industry |
| Applicant | NTPC Limited (NTPC) |
| Land area | 3,134 acres (1,268.3 ha) |
| Forest land | 27 acres (10.9 ha) |
| Project cost | ₹53,899.4 crore |
| Village / locality | Mahloi |
| Taluk / tehsil | Pusour |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site area on record |
| Our reference | WID-CG-03900 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 3,134 acres, this one is larger than 99% of them.
5 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mahloi, Pusour, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Lara Super Thermal Power Project from 3200 MW [Stage-I (2x800 MW)… — more information requested, 350 m away
- Expansion of Lara Super Thermal Power Project from 3200 MW [Stage-I (2x800 MW)… — cleared for impact study, 350 m away
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — environmental approval granted, 350 m away
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — returned to applicant, 1.8 km away
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — environmental approval granted, 1.8 km away
- Mining project by M/s Saurya Minerals Pvt.Ltd — environmental approval granted, 5.5 km away
- Chhotehaldi Limestone Quarry — lapsed, 5.7 km away
- Shri Radhamadhav Crusher Udyog, Proprietor - Mithilesh Kumar Agrawal — lapsed, 6 km away
More from NTPC Limited (NTPC) in Raigarh
- Expansion of Lara Super Thermal Power Project from 3200 MW [Stage-I (2x800 MW)… — more information requested
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — environmental approval granted
- Expansion of Lara Super Thermal Power Project from 3200 MW [Stage-I (2x800 MW)… — cleared for impact study
- NTPC Talaipalli Coal Mining Project — returned to applicant
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — returned to applicant
- 2x800 MW (Expansion, Stage-II) Coal Based Lara Super Thermal Power Project at… — environmental approval granted
16 NTPC projects in Raigarh
All 129 NTPC projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.