Quick answers
What is this project?
Increase in Production Capacity of Ferro Alloys (Silico Manganese From 30,000 Tpa to 39,000 Tpa) With the Same Existing Submerged Electric Arc Furnaces Without Increase in the Pollution Load is a proposed power project in Tara\Mal, Tamnar, Raigarh, Chhattisgarh. The site covers 108.1 acres.
Who is building it?
The applicant is B.S.Sponge Private LTD.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Tara\Mal, Tamnar, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹20 lakh and a site of 108.1 acres.
When was it filed?
The application was filed on 18 Apr 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 18 Apr 2026 |
| Application filed | 18 Apr 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | B.S.Sponge Private LTD |
| Land area | 108.1 acres (43.7 ha) |
| Project cost | ₹20 lakh |
| Village / locality | Tara\Mal |
| Taluk / tehsil | Tamnar |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03151 |
In context
29 applications in Raigarh since January 2022 are in the same category (Power): 13 approved, 9 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 108.1 acres, this one is smaller than 71% of them.
43 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Tara\Mal, Tamnar, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environment Clearance (EC) from B.S. Sponge Private Limited to… — under environmental review, 0 m away
- Applying for "No increase in Pollution Load Certificate" for increase of… — initial checks, 0 m away
- Proposed "Establishment of new DI pipe unit of 2,00,000 TPA Capacity without… — initial checks, 650 m away
- Proposed "Establishment of new DI pipe unit of 2,00,000 TPA Capacity without… — initial checks, 650 m away
- Transfer of Environment Clearance from M/s. Singhal Enterprises Pvt. Ltd. to… — environmental approval granted, 750 m away
- Amendment in EC for Amalgamation of M/s. Singhal Energy Pvt. Ltd — environmental approval granted, 750 m away
- Raigarh-Gharghoda — lapsed, 1.1 km away
- Laying of 33KVA Dedicated Line Banjari to Punjipathra — lapsed, 1.3 km away
More from B.S.Sponge Private LTD in Raigarh
- Greenfield Steel Project-Nawapara Unit-I/O Pellets(1.2MTPA)+PGP(30000NM3/Hr),Sp… — under environmental review
- Greenfield Steel Project-Nawapara Unit-I/O Pellets(1.2MTPA)+PGP(30000NM3/Hr),Sp… — cleared for impact study
- Greenfield Steel Project-Nawapara Unit-I/O Pellets(1.2MTPA)+PGP(30000NM3/Hr),Sp… — cleared for impact study
- Greenfield steel plant by B.S.Sponge Pvt.Ltd. (Badgaon Unit)-Sponge… — cleared for impact study
- Applying for "No increase in Pollution Load Certificate" for increase of… — initial checks
- 132 KV DCSS transmission line from CSPTCL 220/132 KV S/s Gerwani to M/s… — lapsed
All 9 B.S.Sponge projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.