What is Developing? Open the mapMap

Under environmental reviewIndustry · Raipur, Chhattisgarh

Greenfield steel plant comprising of DRI Kilns (2,31,000 TPA), Induction Furnace with matching LRF & CCM (HotBillets / Billets / Ingots – 1,98,000TPA), Rolling Mills (TMT bars / Structural Steel)(85% Hot charging with Hot Billets and remaining 15% through RHF with gasifer as fuel – 1,98,000 TPA),Coal Gasifier (1782 Nm3/Hr), Ferro Alloy Unit 2 x 9 MVA (FeSi – 14,000 TPA/FeMn – 40,000 TPA/SiMn – 28,000 TPA/FeCr – 30,000 TPA/ Pig Iron-48,000 TPA), Briquetting Plant (200 Kg/Hr),W

Greenfield steel plant comprising of DRI Kilns (2,31,000 TPA), Induction Furnace with matching LRF & CCM (HotBillets / Billets / Ingots – 1,98,000TPA), Rolling Mills (TMT bars / Structural Steel)(85% Hot charging with Hot Billets and remaining 15% through RHF with gasifer as fuel – 1,98,000 TPA),Coal Gasifier (1782 Nm3/Hr), Ferro Alloy Unit 2 x 9 MVA (FeSi – 14,000 TPA/FeMn – 40,000 TPA/SiMn – 28,000 TPA/FeCr – 30,000 TPA/ Pig Iron-48,000 TPA), Briquetting Plant (200 Kg/Hr),W is a proposed industrial project in Lakhna, Tilda, Raipur, Chhattisgarh. The site covers 43.4 acres. Its stated project cost is ₹320 crore. As of 27 Nov 2026, its status is “Under environmental review” (since 20 Nov 2026).

See it on the live map All projects in Raipur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Greenfield steel plant comprising of DRI Kilns (2,31,000 TPA), Induction Furnace with matching LRF & CCM (HotBillets / Billets / Ingots – 1,98,000TPA), Rolling Mills (TMT bars / Structural Steel)(85% Hot charging with Hot Billets and remaining 15% through RHF with gasifer as fuel – 1,98,000 TPA),Coal Gasifier (1782 Nm3/Hr), Ferro Alloy Unit 2 x 9 MVA (FeSi – 14,000 TPA/FeMn – 40,000 TPA/SiMn – 28,000 TPA/FeCr – 30,000 TPA/ Pig Iron-48,000 TPA), Briquetting Plant (200 Kg/Hr),W is a proposed industrial project in Lakhna, Tilda, Raipur, Chhattisgarh. The site covers 43.4 acres.

Who is building it?

The applicant is Maa Beriwali Steel & Power Private Limited.

Has it been approved?

Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.

Where is it?

In Lakhna, Tilda, Raipur, Chhattisgarh.

How big is it?

It has a stated cost of ₹320 crore and a site of 43.4 acres.

When was it filed?

The application was filed on 20 Oct 2026.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Greenfield steel plant comprising of DRI Kilns (2,31,000 TPA), Induction Furnace with…

Project details

Official titleEstablishment of Greenfield steel plant comprising of DRI Kilns (2,31,000 TPA), Induction Furnace with matching LRF & CCM (HotBillets / Billets / Ingots – 1,98,000TPA), Rolling Mills (TMT bars / Structural Steel)(85% Hot charging with Hot Billets and remaining 15% through RHF with gasifer as fuel – 1,98,000 TPA),Coal Gasifier (1782 Nm3/Hr), Ferro Alloy Unit 2 x 9 MVA (FeSi – 14,000 TPA/FeMn – 40,000 TPA/SiMn – 28,000 TPA/FeCr – 30,000 TPA/ Pig Iron-48,000 TPA), Briquetting Plant (200 Kg/Hr),W
StatusUnder environmental review
Status since20 Nov 2026
Application filed20 Oct 2026
Approval soughtEnvironmental approval
Application typeNew project
SectorIndustry
ApplicantMaa Beriwali Steel & Power Private Limited
Land area43.4 acres (17.6 ha)
Project cost₹320 crore
Village / localityLakhna
Taluk / tehsilTilda
DistrictRaipur
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-03350

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 20 Oct 2026 (this page)Under environmental review43.4 acres₹320 crore
Amendment filed 19 Sept 2023Cleared for impact study43.4 acres₹320 crore

In context

219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 43.4 acres, this one is larger than 63% of them.

Where it is

Lakhna, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.