Greenfield Steel Plant Comprising of Pellet Plant1x2,000tpd–6,60,000tpa is a proposed industrial project in Sankar, Tilda, Raipur, Chhattisgarh. The site covers 201.3 acres.
Who is building it?
The applicant is Shree Nakoda Ispat and Power Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Sankar, Tilda, Raipur, Chhattisgarh.
How big is it?
It has a stated cost of ₹683.8 crore and a site of 201.3 acres.
When was it filed?
The application was filed on 17 Oct 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Greenfield Steel Plant Comprising of Pellet Plant1x2,000tpd–6,60,000tpa
Project details
| Official title | Establishment of Greenfield Steel Plant Comprising of Pellet Plant1x2,000tpd–6,60,000tpa, Along With Producer Gas Plant for Pellet Plant-1x20,000nm3/Hr,dri Kilns2x350tpd-2,31,000tpa, Induction Furnaces With Matching Lrf&ccm(Hot Billets/Billets/Ingots)2x30t-1,98,000tpa,rolling Mills(Tmt Bars/Structural Steel)(85%hot Charging With Hot Billets and Remaining15%through Rhf With Coal Gasifier As Fuel–1,98,000tpa,along With Coal Gasifier for Reheating Furnace-1x6,000nm3/Hr,galvanizing Plant Pipe Unit3 |
|---|---|
| Status | Under environmental review |
| Status since | 26 Nov 2026 |
| Application filed | 17 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Shree Nakoda Ispat and Power Private Limited |
| Land area | 201.3 acres (81.5 ha) |
| Project cost | ₹683.8 crore |
| Village / locality | Sankar |
| Taluk / tehsil | Tilda |
| District | Raipur |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03052 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 17 Oct 2026 (this page) | Under environmental review | 201.3 acres | ₹683.8 crore |
| Early planning filed 21 Aug 2024 | Cleared for impact study | 185.9 acres | ₹683.8 crore |
In context
219 applications in Raipur since January 2022 are in the same category (Industry): 135 approved, 44 filed or under review, and 40 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 201.3 acres, this one is larger than 90% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sankar, Tilda, Raipur, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed backward integration by establishment of 1 x 500 TPD DRI Kiln to… — cleared for impact study, 2.8 km away
- Greenfield steel plant comprising of Pelletization plant 0.9 MTPA, along Coal… — cleared for impact study, 3.4 km away
- Expansion of Integrated Steel plant-Sponge Iron Plant-0.6 MTPA,Power Plant-125… — lapsed, 3.5 km away
- Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA… — environmental approval granted, 3.5 km away
- Expansion of existing integrated Steel Plant -DRI Kilns(Sponge Iron 0.6 MTPA… — cleared for impact study, 3.5 km away
- Proposed expansion in permitted capacities with inclusion of HRAP Steel… — cleared for impact study, 4.8 km away
- Green Field Project 2.2 MTPA Integrated Steel Plant at Khasra No. 746, 747,… — more information requested, 6 km away
- EC – Corrigendum for correction in lease area in EC Name change letter No.… — environmental approval granted, 6.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.