Quick answers
What is Serula Pumped Storage Hydro Electric Project (960 MW)?
Serula Pumped Storage Hydro Electric Project (960 MW) is a proposed power project in Na, Songadh, Tapi, Gujarat. The site covers 1,340.6 acres.
Who is building it?
The applicant is Gujarat State Electricity Corporation Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Na, Songadh, Tapi, Gujarat.
How big is it?
It has a stated cost of ₹4,606.8 crore and a site of 1,340.6 acres.
When was it filed?
The application was filed on 13 Oct 2026.
One of 4 filings for this project. The project's main page, with every filing and where each stands: Serula Pumped Storage Hydro Electric Project (960 MW)
Project details
| Status | More information requested |
|---|---|
| Status since | 13 Nov 2026 |
| Application filed | 13 Oct 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Gujarat State Electricity Corporation Limited |
| Land area | 1,340.6 acres (542.5 ha) |
| Project cost | ₹4,606.8 crore |
| Village / locality | Na |
| Taluk / tehsil | Songadh |
| District | Tapi |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12711 |
All filings for this project
This project has 4 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 13 Oct 2026 (this page) | More information requested | 1,340.6 acres | ₹4,606.8 crore |
| New project filed 11 Jun 2025 | Lapsed | 4,598 acres | ₹4,606.8 crore |
| New project filed 4 Mar 2025 | Lapsed | 4,598 acres | ₹4,606.8 crore |
| Early planning filed 5 Aug 2024 | Cleared for impact study | 1,340.6 acres | ₹4,606.8 crore |
In context
11 applications in Tapi since January 2022 are in the same category (Power): 2 approved, 2 filed or under review, and 7 withdrawn, lapsed or rejected.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Na, Songadh, Tapi, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Serula Pumped Storage Hydro Electric Project (960 MW) — cleared for impact study, 0 m away
- Serula Pumped Storage Hydro Electric Project (960 MW) — lapsed, 750 m away
- Serula Pumped Storage Hydro Electric Project (960 MW) — lapsed, 750 m away
- Permission for Drilling of Boreholes in Trapty Range, Vyara Forest Division,… — lapsed, 3.8 km away
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — cleared for impact study, 4.4 km away
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — lapsed, 4.9 km away
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — lapsed, 4.9 km away
- Line erection work of 66KV Ukai SS to 66kV Satkashi pumping station-1,2 & 3 of… — lapsed, 6.6 km away
More from Gujarat State Electricity Corporation Limited in Tapi
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — lapsed
- Satkashi Pumped Storage Hydro Electric Project (330 MW) — lapsed
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — lapsed
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — cleared for impact study
- Satkashi Pumped Storage Hydro Electric Project (330 MW) — cleared for impact study
- Juni Bavli Pumped Storage Hydro Electric Project (450 MW) — cleared for impact study
11 Gujarat State Electricity Corporation projects in Tapi
All 25 Gujarat State Electricity Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.