Quick answers
What is this project?
Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) is a lapsed power project in Na, Songadh, Tapi, Gujarat.
Who is building it?
The applicant is Gujarat State Electricity Corporation Limited.
Has it been approved?
No. The application was lapsed on 9 Oct 2025, so it is no longer under consideration.
Where is it?
In Na, Songadh, Tapi, Gujarat.
How big is it?
It has a stated cost of ₹1,671.1 crore.
When was it filed?
The application was filed on 11 Jun 2025.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW)
Project details
| Status | Lapsed |
|---|---|
| Status since | 9 Oct 2025 |
| Application filed | 11 Jun 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Gujarat State Electricity Corporation Limited |
| Project cost | ₹1,671.1 crore |
| Village / locality | Na |
| Taluk / tehsil | Songadh |
| District | Tapi |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14124 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 11 Jun 2025 (this page) | Lapsed | ₹1,671.1 crore | |
| New project filed 4 Mar 2025 | Lapsed | ₹1,671.1 crore | |
| Early planning filed 5 Aug 2024 | Cleared for impact study | 1,300.1 acres | ₹1,671.1 crore |
In context
11 applications in Tapi since January 2022 are in the same category (Power): 2 approved, 2 filed or under review, and 7 withdrawn, lapsed or rejected.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Na, Songadh, Tapi, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — lapsed, 0 m away
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — cleared for impact study, 1000 m away
- Juni Bavli Pumped Storage Hydro Electric Project (450 MW) — cleared for impact study, 2 km away
- Line erection work of 66KV Ukai SS to 66kV Satkashi pumping station-1,2 & 3 of… — lapsed, 3.3 km away
- Permission for Drilling of Boreholes in Trapty Range, Vyara Forest Division,… — lapsed, 3.3 km away
- Laying OFC for 4G coverage of uncovered villages through USOF, Babarghat T… — lapsed, 4.1 km away
- Satkashi Pumped Storage Hydro Electric Project (330 MW) — cleared for impact study, 4.8 km away
- Serula Pumped Storage Hydro Electric Project (960 MW) — more information requested, 4.9 km away
More from Gujarat State Electricity Corporation Limited in Tapi
- Serula Pumped Storage Hydro Electric Project (960 MW) — more information requested
- Satkashi Pumped Storage Hydro Electric Project (330 MW) — lapsed
- Serula Pumped Storage Hydro Electric Project (960 MW) — lapsed
- Serula Pumped Storage Hydro Electric Project (960 MW) — lapsed
- Satkashi Pumped Storage Hydro Electric Project (330 MW) — cleared for impact study
- Serula Pumped Storage Hydro Electric Project (960 MW) — cleared for impact study
11 Gujarat State Electricity Corporation projects in Tapi
All 25 Gujarat State Electricity Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.