Quick answers
What is this project?
Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) is a proposed water and irrigation project in Na, Songadh, Tapi, Gujarat. The site covers 1,300.1 acres.
Who is building it?
The applicant is Gujarat State Electricity Corporation Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 2 Oct 2024), as of 27 Nov 2026.
Where is it?
In Na, Songadh, Tapi, Gujarat.
How big is it?
It has a stated cost of ₹1,671.1 crore and a site of 1,300.1 acres.
When was it filed?
The application was filed on 5 Aug 2024.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 2 Oct 2024 |
| Application filed | 5 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Water & irrigation |
| Applicant | Gujarat State Electricity Corporation Limited |
| Land area | 1,300.1 acres (526.1 ha) |
| Project cost | ₹1,671.1 crore |
| Village / locality | Na |
| Taluk / tehsil | Songadh |
| District | Tapi |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-05049 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 11 Jun 2025 | Lapsed | ₹1,671.1 crore | |
| New project filed 4 Mar 2025 | Lapsed | ₹1,671.1 crore | |
| Early planning filed 5 Aug 2024 (this page) | Cleared for impact study | 1,300.1 acres | ₹1,671.1 crore |
In context
9 applications in Tapi since January 2022 are in the same category (Water & irrigation): 6 approved, 1 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Na, Songadh, Tapi, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — lapsed, 1000 m away
- Juni Kayaliwel Pumped Storage Hydro Electric Project (300 MW) — lapsed, 1000 m away
- Juni Bavli Pumped Storage Hydro Electric Project (450 MW) — cleared for impact study, 2.4 km away
- Line erection work of 66KV Ukai SS to 66kV Satkashi pumping station-1,2 & 3 of… — lapsed, 2.7 km away
- Permission for Drilling of Boreholes in Trapty Range, Vyara Forest Division,… — lapsed, 3.8 km away
- Serula Pumped Storage Hydro Electric Project (960 MW) — more information requested, 4.4 km away
- Serula Pumped Storage Hydro Electric Project (960 MW) — cleared for impact study, 4.4 km away
- Laying OFC for 4G coverage of uncovered villages through USOF, Babarghat T… — lapsed, 4.6 km away
More from Gujarat State Electricity Corporation Limited in Tapi
- Serula Pumped Storage Hydro Electric Project (960 MW) — more information requested
- Satkashi Pumped Storage Hydro Electric Project (330 MW) — lapsed
- Serula Pumped Storage Hydro Electric Project (960 MW) — lapsed
- Serula Pumped Storage Hydro Electric Project (960 MW) — lapsed
- Satkashi Pumped Storage Hydro Electric Project (330 MW) — cleared for impact study
- Serula Pumped Storage Hydro Electric Project (960 MW) — cleared for impact study
11 Gujarat State Electricity Corporation projects in Tapi
All 25 Gujarat State Electricity Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.