1)125 Mm Dia Pipeline for Afva Village Connectivity Taluka Bardoli 2) 4" Inch Steel Pipeline for Tundi Village Connectivity is an approved pipeline project in Afva, Bardoli, Surat, Gujarat. The site covers 0.1 acres.
Who is building it?
The applicant is Gujarat Gas Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 19 Aug 2025), as of 27 Nov 2026.
Where is it?
In Afva, Bardoli, Surat, Gujarat.
How big is it?
It has a stated cost of ₹43 lakh; a site of 0.1 acres and 310 m² of forest land.
When was it filed?
The application was filed on 11 Jul 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 19 Aug 2025 |
| Application filed | 11 Jul 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Gujarat Gas Limited |
| Land area | 300 m² |
| Forest land | 310 m² |
| Project cost | ₹43 lakh |
| Village / locality | Afva |
| Taluk / tehsil | Bardoli |
| District | Surat |
| State | Gujarat |
| Location from | Site area on record |
| Our reference | WID-GJ-12928 |
In context
36 applications in Surat since January 2022 are in the same category (Pipelines): 16 approved, 8 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 8 months from filing to approval. At 0.1 acres, this one is smaller than 85% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Afva, Bardoli, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.0123 Ha. of PF Land for laying of 125 mm PE Pipeline Network to… — more information requested, 1.3 km away
- Palsana to Ghaluda to Ena to Dhamdod to Vanesa to Isroli Total length 16/145… — lapsed, 2.7 km away
- The Diversion Of 0.39 Hectare Protected Forest Land To Construct An Approach… — under forest review, 3.9 km away
- Proposed expansion of Stand Alone Cement Manufacturing (Clinker Grinding) Unit… — environmental approval granted, 5.2 km away
- Proposed expansion of Stand Alone Cement Manufacturing (Clinker Grinding) Unit… — environmental approval granted, 5.2 km away
- Grant of Permission to Lay Optical Fiber Cable From Lakhanpor Village to Puni… — lapsed, 6.2 km away
- Enhancement of Captive Power Plant Capacity and Duplex Board Manufacturing… — under environmental review, 6.2 km away
- Expansion of Captive Power Plant From 4.8 MW to 6.5 MW — withdrawn, 6.2 km away
More from Gujarat Gas Limited in Surat
- Diversion of 0.0337 Ha. of Protected Forest Land I.E. Road Side Strip… — in-principle approval, conditions pending
- Diversion of 0.0123 Ha. of PF Land for laying of 125 mm PE Pipeline Network to… — more information requested
- Diversion of 0.0020 ha. of PF land for laying of 6" Dia. NB Steel Gas Pipeline… — more information requested
- Gas Distribution Network in Mangrol Taluka & Surrounding Area (Mangrol Taluka… — lapsed
- : Diversion of 0. 0.9016 Ha. of Protected Forest Land for Laying 125 Mm Dia.… — lapsed
- Gas Distribution Network in Mandavi Taluka& Surrounding Area (D C Shah petrol… — more information requested
20 Gujarat Gas projects in Surat
All 289 Gujarat Gas projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.