Diversion of 8.4109 Ha. Of Reserved Forest Land for construction of 66 KV Astol–Fatepur D/C line on D/C & MC tower with ACSR panther conductor at Proposed 66 KV Fatepur Substation

Diversion of 8.4109 Ha. Of Reserved Forest Land for construction of 66 KV Astol–Fatepur D/C line on D/C & MC tower with ACSR panther conductor at Proposed 66 KV Fatepur Substation is a proposed power project in Astol, Kaprada, Valsad, Gujarat. The site covers 20.8 acres. Its stated project cost is ₹17 crore. As of 27 Nov 2026, its status is “More information requested” (since 16 Nov 2026).

See it on the live map All projects in Valsad

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Diversion of 8.4109 Ha. Of Reserved Forest Land for construction of 66 KV Astol–Fatepur D/C line on D/C & MC tower with ACSR panther conductor at Proposed 66 KV Fatepur Substation is a proposed power project in Astol, Kaprada, Valsad, Gujarat. The site covers 20.8 acres.

Who is building it?

The applicant is Gujarat Energy Transmission Corp LTD.

Has it been approved?

Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.

Where is it?

In Astol, Kaprada, Valsad, Gujarat.

How big is it?

It has a stated cost of ₹17 crore; a site of 20.8 acres and 20.8 acres (8.4 ha) of forest land.

When was it filed?

The application was filed on 20 Jun 2026.

Project details

Official titleDiversion of 8.4109 Ha. Of Reserved Forest Land for construction of 66 KV Astol–Fatepur D/C line on D/C & MC tower with ACSR panther conductor at Proposed 66 KV Fatepur Substation in Valsad District.
StatusMore information requested
Status since16 Nov 2026
Application filed20 Jun 2026
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantGujarat Energy Transmission Corp LTD
Land area20.8 acres (8.4 ha)
Forest land20.8 acres (8.4 ha)
Project cost₹17 crore
Village / localityAstol
Taluk / tehsilKaprada
DistrictValsad
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-13326

In context

16 applications in Valsad since January 2022 are in the same category (Power): 9 approved, 3 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 13 months from filing to approval. At 20.8 acres, this one is larger than 69% of them.

2 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Astol, Kaprada, Valsad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Gujarat Energy Transmission Corp LTD in Valsad

12 Gujarat Energy Transmission Corp projects in Valsad
All 231 Gujarat Energy Transmission Corp projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.