Quick answers
What is this project?
Laying Irrigation Under Ground Water Pipeline for Filling of Various CD/Ponds/MI Scheme of Muli, Sayla and Wadhvan Taluka (44-Village)of District Surendrnagar is a proposed pipeline project in Dhajala, Sayla, Surendranagar, Gujarat. The site covers 8.7 acres.
Who is building it?
The applicant is Executive Engineer Sauni Yojna Division Rajkot.
Has it been approved?
Not yet. The application is still under review: its status is “In-principle approval, conditions pending”, as of 27 Nov 2026.
Where is it?
In Dhajala, Sayla, Surendranagar, Gujarat.
How big is it?
It has a stated cost of ₹218 crore; a site of 8.7 acres and 1.2 acres (0.5 ha) of forest land.
When was it filed?
The application was filed on 15 Apr 2026.
Project details
| Status | In-principle approval, conditions pending |
|---|---|
| Status since | 16 Nov 2026 |
| Application filed | 15 Apr 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Executive Engineer Sauni Yojna Division Rajkot |
| Land area | 8.7 acres (3.5 ha) |
| Forest land | 1.2 acres (0.5 ha) |
| Project cost | ₹218 crore |
| Village / locality | Dhajala |
| Taluk / tehsil | Sayla |
| District | Surendranagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-13772 |
In context
26 applications in Surendranagar since January 2022 are in the same category (Pipelines): 16 approved, 9 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 19 months from filing to approval. At 8.7 acres, this one is larger than 91% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Dhajala, Sayla, Surendranagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 33 KV S/C Overhead Transmission Line for Wind Project of 150 MW — forest land use approved, 2.1 km away
- 70 MW Wind Power Project — more information requested, 4.8 km away
- Ajitbhai Bhikhubhai Gohil — under environmental review, 6.2 km away
- Smt Gajruben Naagbhai Khavad — environmental approval granted, 9.5 km away
- Nadala Blacktrap Block-A — environmental approval granted, 9.9 km away
- Nadala Blacktrap Block-B — environmental approval granted, 10 km away
- Shri Manish Singh (Sejakpar Ordinary Sand Block- A) — under environmental review, 10.4 km away
- Shri Khavad Champrajbhai Bhupatbhai — returned to applicant, 10.4 km away
More from Executive Engineer Sauni Yojna Division Rajkot in Surendranagar
- Engineering, Procurement And Construction (EPC) Contract For Providing… — more information requested
- Diversion of 0.132 ha. for Engineering, Procurement And Construction (EPC) for… — more information requested
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.