What is this project?
Diversion of 0.0236 Ha Forest Land for 66KV Rampar Superspintex Line With 1cx630sqmm (3+1) Xlpe Under Ground Power Cable is an approved power project in Moti Banugar, Jamnagar Rural, Jamnagar, Gujarat. The site covers 0 acres.
Who is building it?
The applicant is Gujarat Energy Transmission Corp LTD.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 7 Oct 2026), as of 27 Nov 2026.
Where is it?
In Moti Banugar, Jamnagar Rural, Jamnagar, Gujarat.
How big is it?
It has a stated cost of ₹46 lakh; a site of 0 acres and 240 m² of forest land.
When was it filed?
The application was filed on 2 Oct 2025.
Project details
| Status | Forest land use approved |
|---|---|
| Status since | 7 Oct 2026 |
| Application filed | 2 Oct 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Gujarat Energy Transmission Corp LTD |
| Land area | 200 m² |
| Forest land | 240 m² |
| Project cost | ₹46 lakh |
| Village / locality | Moti Banugar |
| Taluk / tehsil | Jamnagar Rural |
| District | Jamnagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14445 |
In context
30 applications in Jamnagar since January 2022 are in the same category (Power): 9 approved, 10 filed or under review, and 10 withdrawn, lapsed or rejected. The approved ones took a median of 11 months from filing to approval. At 0 acres, this one is smaller than 100% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Moti Banugar, Jamnagar Rural, Jamnagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- diversion of 0.1739-hectare forest land for Laying of 66KV S/C Rampar-Stena… — more information requested, 1.1 km away
- Expansion of existing Metallurgical Manufacturing Unit at Survey No: 249, 373,… — under environmental review, 2.5 km away
- Proposed Proposal for Enhancement of production capacity of the existing… — initial checks, 2.5 km away
- Laying of 66KV S/C Falla – Dhrangada underground cable line with 66KV,… — more information requested, 7 km away
- Industrial project by M/s. Shreeji Coke & Energy Private Limited — environmental approval granted, 7.1 km away
- Correction in Existing Environment clearance of Plot no. correction without… — environmental approval granted, 7.2 km away
- Widening and Strethning of Maliya-Amran-Bhadra Circle-Jodiya-Jambuda Patiya road — forest land use approved, 9.3 km away
- Up-gradation of Fish Landing Centre at Sachana, District Jamnagar, Gujarat — more information requested, 10.5 km away
More from Gujarat Energy Transmission Corp LTD in Jamnagar
- Diversion of 0.15156 ha Reserved Forest land for Laying of 66kV Underground… — initial checks
- diversion of 0.1739-hectare forest land for Laying of 66KV S/C Rampar-Stena… — more information requested
- Diversion of 1.3573 ha forest land for erection of 66kV LILO Gorakhadi Line… — more information requested
- Diversion of 0.8676 ha forest land for 66kV LILO Gorakhadi line from 66kV… — lapsed
- 66KV S/C Line From 66KV Jayva (Getco) S/S to Switchyard of M/S Aluwerk LLP… — forest land use approved
- 66KV S/C line from 66KV Jayva(GETCO) Substation to switchyard of M/S RAVI… — forest land use approved
17 Gujarat Energy Transmission Corp projects in Jamnagar
All 231 Gujarat Energy Transmission Corp projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.